Sec. 70-694. Specific requirements for large scale solar energy systems.

About this text

  • As published by Municode, current through 2026-06-23
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

The following requirements apply to large scale SESs, in addition to the general requirements in this article that apply to all ground mounted SES.

(1) Setbacks. A large scale SES shall comply with the following setback requirements:

a. The large scale SES shall be located no closer than the lesser of (a) 25 feet from any property line, or (b) the required setback for the applicable zoning district, if any;

b. The large scale SES shall be located no closer than the lesser of (a) 30 feet from any public right-of-way, or (b) the required setback for the applicable zoning district, if any; and

c. The large scale SES shall be located no closer than 100 feet from any residential dwelling unit on an adjacent lot.

(2) Visual buffers.

a. A large scale SES facility shall have, to the extent reasonably practicable, a year-round visual buffer of natural trees, vegetation, plantings, or earth berms which provide a reasonable visual and lighting screen to restrict the view of the SES facility from adjacent public or private property (including those lots located across a public right-of-way). Any such vegetative buffer shall be not less than 150 feet in width. Such required visual and lighting buffer may include existing natural tree growth and natural land berms located: (i) along the perimeter of the SES facility footprint:, (ii) along the perimeter of the real property owned or leased by the solar developer for the solar project, or (iii) partly along the perimeter of the SES facility and partly along the perimeter of the real property owned or leased by the solar developer for the solar project if such natural buffer is approved by the Lee County Planning Department as being in compliance with this article. Such natural tree growth and natural land berms shall be preserved by the solar developer or its successor when reasonably practicable. If an approved natural buffer located either along the perimeter of the SES facility footprint, along the perimeter of the real property owned or leased by the solar developer for the solar project, or partly along the perimeter of the SES facility and partly along the perimeter of the real property owned or leased by the solar developer for the solar project does not exist, dies, or is destroyed, or does not provide a visual and lighting screen to restrict the view of the SES facility as required by this chapter, then the solar developer shall establish and maintain such a buffer of the required width in the area where such buffer does not exist, dies, or is destroyed in the manner provided in this subsection. Any such visual and lighting buffer shall be located (i) along the perimeter of the SES facility footprint, (ii) along the perimeter of the real property owned or leased by the solar developer for the solar project, or (iii) partly along the perimeter of the SES facility and partly along the perimeter of the real property owned or leased by the solar developer for the solar project.

Such vegetative buffer planted or established by the solar developer may consist of planted trees, hedges, and similar plantings and vegetation established and maintained by the solar developer or its successor as a year-round visual and lighting buffer as required by this subsection in accordance with the most recent visual and lighting buffer plan approved by the Lee County Board of Commissioners, and as further described in the conditional use provisions of this article. Any existing or planted vegetative buffer shall consist of vegetation which is of a type and species which will normally grow to a height in the Lee County geographic area within a reasonable time period sufficient to shield the SES facility located upon the SES footprint from the view of adjacent landowners and persons travelling by the SES on public or private rights of way.

In order to provide for the health, safety, and welfare of the public, and in order to provide additional visual screening of the SES facility, the Lee County Board of Commissioners may also require the installation and maintenance of fencing enclosing the SES facility. Such fencing may be located along the perimeter of the SES facility footprint, or at such other locations as may be determined by the board of commissioners in connection with the grant of a conditional use permit to the solar developer in accord with this chapter. Such fencing, if required, shall provide for an appropriate gates or gates for ingress and egress to and from the SES facility by the owner of the facility and the owner's agents, employees, and contractors.

b. All such visual buffers shall be installed and maintained in accord with the provisions of section 70-86 of the county's Code of Ordinances. The required maintenance of such buffers shall be installed within the two-year period as provided in section 70-86 and such maintenance shall continue in accord with the requirements of section 70-86 during the time that the large scale solar facility remains in operation. No conditional use permit shall be issued to any large scale SES project until the owner thereof agrees in writing that the owner, and the owner's successors and assigns, shall comply with the provisions of section 70-86 for the period of time that the large scale SES remains in operation.

(3) Signage. A large scale SES:

a. Shall display signs (a) stating the risks that may result from contact with a large scale SES facility, (b) identifying the owner or operator of the intermediate scale SES, and (c) providing a 24-hour emergency contact phone number;

b. Shall comply with the requirements of the applicable zoning district and local sign ordinances; and

c. May have signs that contain educational information about the large scale SES facility as long as such signs comply with requirements of the applicable zoning district and local sign ordinances.

History

The history line the source prints at the end of the section.

(Ord. of 1-28-2020; Ord. of 1-26-2021; Ord. of 10-26-2021, pts. 2, 5)

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:lee-county/zoning/70-694@2026-06-23-94f966cf21

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Lee County Zoning Ordinance, Sec. 70-694. Specific requirements for large scale solar energy systems | Georgia Commons