Leesburg · Zoning Ordinance
Appendix A - ZONING / Article VII - ACCELERATED MAJOR SUBDIVISION PROCEDURES
Sec. 7.06. Issuance of building permits (this article only).
About this text
- As published by Municode, retrieved 2026-11-11
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
(a) Under the accelerated major subdivision procedures, building permits may be applied for once all items addressed in section 4.04 are met; provided, however, that under the accelerated major subdivision procedures, building permits may be applied for and issued (assuming all requirements have been met by the applicant) prior to the subdivision water system and the subdivision wastewater system being connected to the water system and sewer system of the City of Leesburg Water and Sewer where the following requirements are met:
(1) The applicant has complied with the provisions of section 7.01, section 7.02, and section 7.03.
(2) The applicant has completed the installation of the water lines within the subdivision, and such installation has been tested and approved by the appropriate governing authority.
(3) The applicant has completed the installation of the sewer lines within the subdivision, and such installation has been tested and approved by the appropriate governing authority.
(4) The applicant, in the judgment of the manager of development services, has been unable to connect the subdivision's water system to the City of Leesburg Water and Sewer's main water system solely because the authority's water system line to which such connection must be made has not been completed.
(5) The applicant, in the judgment of the manager of development services, has been unable to connect the subdivision's sewer system to the City of Leesburg Water and Sewer's main sewer system solely because the authority's sewer system line to which such connection must be made has not been completed.
(6) The applicant agrees in writing that the applicant will connect the subdivision's water lines and the subdivision's sewer lines to the authority's water lines and sewer lines to which such connections must be made within 30 calendar days from the date that the applicant is notified by Leesburg or by the City of Leesburg Water and Sewer that such connections are available.
(7) The developer acknowledges in writing that no certificate of occupancy shall be issued for any dwelling constructed in the subdivision until such time as the subdivision water lines and the subdivision sewer lines are connected to the authority's water lines and sewer lines to which such connections must be made and such connections have been tested and approved by the appropriate governing authority.
Except as specifically provided in this subsection, no building permit shall be issued under this section without compliance with all of the items addressed in section 4.04. The provisions of this section are not intended to supersede or conflict with the provisions of any federal or state statutes or regulations regarding the installation, testing, approval, maintenance, or operation of water systems and sewer systems, and where any such conflict exists, the provisions of such federal or state statutes or regulations shall control.
(b) In subdivisions developed under this article, only the homeowner or the builder can apply for or be issued a building permit. Any such applicant must execute an affidavit that he is aware that an occupation permit is not guaranteed and will, in fact, be denied as will the connection of permanent utilities until such time as the subdivision is completed as required under this article and the city council has accepted all rights-of-way and easements by resolutions.
(c) All persons working on buildings in subdivisions developed under this article shall use the temporary construction easements and stay off any subdivision road rights-of-way, drainage systems, or other site improvements under construction.
Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.