(a) The final plat shall be signed by the planning director and may be recorded by the developer once the following items are complete:

(1) Construction plans have been approved by the manager of development services.

(2) All final plat requirements and accompanying legal and other documentation required by this ordinance have been submitted and approved by the city planner. All legal documents and maintenance bonds must be approved by the city attorney.

(3) Construction access easements are in a condition to carry construction traffic.

(4) A complete copy of the construction contract and two additional construction cost estimates, if requested, have been submitted and approved by the city attorney and manager of development services and placed on file in the applicant's subdivision file.

(5) An irrevocable letter of credit for 125 percent of construction cost has been submitted and approved by the city attorney and the manager of development services.

(6) The owner's affidavit required in section 7.03 is provided and recorded.

(b) If approval under this section is denied, the applicant will be given the reasons for denial in writing.

(c) If the reasons for denial cannot be worked out to the city council satisfaction, the accelerated major subdivision procedure cannot be followed. In this event, the applicant may proceed with the subdivision under the normal major subdivision procedure outlined in article IV of this ordinance.

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:leesburg/zoning/appendix-a-article-vii-7.04@2026-11-11-d4397db3a5

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Leesburg Zoning Ordinance, Sec. 7.04 (Appendix A, Article VII). Recording the final plat (this article only) | Georgia Commons