Sec. 10.07. Construction constraints.

About this text

  • As published by Municode, retrieved 2026-11-11
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

(a) Quality assurance.

(1) Qualification of workmen. Provide at least one person who shall be present at all times during the construction who is thoroughly familiar with the work involved and who shall direct the work.

(2) Codes and standards. Conform to all federal, state and local laws and regulations.

(3) Qualifications of testing agency. Where the services of a testing agency are required, use only qualified testing laboratories with not less than three years' experience in conducting and evaluating the required tests.

(b) Submittals. Submit laboratory reports to the manager of development services for all tests performed on this project as required by this section or by applicable federal, state or local agencies.

(c) Prevention of contaminated water at lines in service. Sections of water lines adjacent to existing water lines that are in service shall be chlorinated, flushed and checked for absence of bacteria before the new section of the line can be pressure tested. A pressure test may be performed on the line before chlorinating, provided the new line is not connected to any existing line during the pressure test. This procedure is set forth to prevent contaminated water or water with high chlorine content from being forced into a line in service through a faulty valve or other defect during pressure tests.

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:leesburg/zoning/appendix-c-article-x-division-1-10.07@2026-11-11-55f90290e1

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Leesburg Zoning Ordinance, Sec. 10.07 (Appendix C, Article X, Division 1). Construction constraints | Georgia Commons