Section 845. Manufactured Home Parks.

About this text

  • As posted on the city's website, retrieved 2026-11-14

In addition to the requirements in Section 840 above, manufactured home parks and manufactured homes within such parks are subject to the requirements of this subsection.

845.1 Permit requirements.

(1) Park Construction Permit Required. The applicant shall submit to the Building & Code Official a site plan of the park meeting all conditions of this section. No person shall create or alter a manufactured home park until an application for the construction of such park has been reviewed by the Building & Code Official, and a construction permit (“park construction permit”) has been issued. The application requires the following:

(a) the name and address of the applicant;

(b) the location and legal description of the proposed park property;

(c) a complete plan of the proposed park at a scale of not more than one hundred (100) feet to one (1) inch showing the shape, area, and size of the site, street and driveway layout, including distance notations, the location and grouping of manufactured home spaces and accessory buildings, the placement and sizes of utilities, all manufactured home space boundaries, and other data pertinent to the requirements of this Ordinance;

(d) plans and specifications of all buildings, improvements, and facilities; and,

(e) such further information as requested by the Building Official to help determine whether the proposed park will comply with all legal requirements. The application and all accompanying plans and specifications shall be filed in triplicate.

(2) Permit Expiration. If no substantial construction progress has been made within six (6) months of issuance of the permit, it becomes invalid and must be renewed. For the purpose of this section, "substantial construction" requires final site grading, the installation of utilities, and at least forty percent (40%) completion (by a cost analysis) of total site improvements.

(3) Building Permit Required. No person shall park a manufactured home on a manufactured home space until a building permit has been issued.

(4) Certificate of Occupancy Required. A Certificate of Occupancy is required in advance of the use or occupancy of manufactured homes. No Certificate of Occupancy shall be issued without full compliance with this Ordinance. A record of all Certificates of Occupancy shall be kept on file in the office of the Building & Code Official. A copy shall be furnished, on request, to any person having a property or tenancy interest in the building or land.

Read this code where it is posted (city website) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:madison/zoning/845@2026-11-14-bfa67127cb

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Madison Zoning Ordinance, Section 845. Manufactured Home Parks | Georgia Commons