Section 4.41. Water distribution systems.

About this text

  • As published by Municode, retrieved 2026-11-11
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

A. Generally. Water mains properly connected with the city water supply system or with an alternate supply system approved by the city council shall be constructed in such a manner so as to adequately serve all lots shown on the subdivision plat for both residential use and fire protection. All materials, labor, equipment, and other items related to construction of the water distribution system shall be provided in accordance to city specifications.

B. Extension without subdivisions. The subdivider shall be responsible for the material and labor cost of extending the water systems within the subdivision as directed and inspected by the water and sewer department.

1. The extensions of water mains within the subdivision shall be designed to provide adequate hydraulic capacity for future extensions to the surrounding area and must be connected to existing surrounding water mains to accomplish desirable hydraulic looping.

2. Dead-end mains within a subdivision shall be avoided where practical, as determined by the water and sewer department. Water mains in dead-end streets shall have a fire hydrant installed at the end of the line on a common lot

corner.

C. Minimum pipe diameter. Typically, the minimum water main pipe diameter within a subdivision shall be six inches. The need for smaller or larger sized mains shall be determined by the water and sewer department, to assure adequate water supply and fire protection to the subdivision, and to assure adequate water flow for future development in the area.

D. Installation. All service lines shall be installed by the developer's contractor according to the water and sewer department's standard detail.

E. Valves. Valves shall be installed to effect a minimum cut-off of mains in cases of emergency shutdown as determined by the water and sewerage department.

F. Fire hydrants. Fire hydrants will be installed so that all residential property within a subdivision will be less than 300 feet from a fire hydrant, with a maximum spacing of 525 feet between hydrants.

G. City design of water mains. The water and sewer department and the Georgia Environmental Protection Division shall approve the design and materials of water mains, and all materials, fittings, and accessories for public water systems in a subdivision.

H. Location and depth of water mains. All water mains shall be located at least four feet below finished grade and shall be eight feet in back of the curb line or seven feet from the edge of pavement and within the public street rightof-way.

I. Fire flow requirements:

1. The minimum fire flow and residual pressure for single family detached houses or duplexes shall be 750 gallons per

minute (g.p.m) at 20 pounds per square inch (p.s.i.) residual pressure as required by the state fire marshal.

2. The minimum fire flow for all other types of development shall be determined on a

case-by-case basis by the water and sewer department.

3. Hydrostatic testing. The water and sewer department shall authorize hydrostatic

testing of water mains and hydrants in a subdivision. Leakage testing shall be

two hours at 11 /2 times the system operating pressure.

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:manchester/zoning/4.41@2026-11-11-2747665c89