(a) Data centers shall achieve a water usage effectiveness (WUE) of no more than 1.8 L/kWh, verified annually by submission of metered data to the county or applicable utility provider. (b) Applicants shall prioritize air-cooled, liquid immersion, or hybrid cooling systems. Any facility proposing water-cooled systems shall incorporate a mandatory water reclamation and reuse system, and the applicant must demonstrate that the selected cooling method is the least water-intensive technology feasible for the site. (c) Preference shall be given to closed-loop cooling systems or non-potable/recycled water sources. No discharge of cooling water into public sewers shall be permitted without treatment. (d) Direct connections to surface water sources or sub-surface aquifers are prohibited. (e) Prior to permitting, the applicant shall provide written verification from the state environmental protection division (EPD) and the applicable utility provider that the facility will not impair the local water supply during droughts or peak demand periods, including projected annual consumption figures. (f) Development of data center uses shall be limited to areas served by the county water utility. No on-site wells shall be utilized to provide water for any purpose, unless explicitly authorized by the county. (g) Facilities shall comply with water efficiency standards established by the applicable utility provider, including any maximum allowable usage thresholds in effect at the time of approval. Compliance with these standards shall be a condition of any special use approval. (h) Applicants shall enter into binding agreements with affected utility providers to fund and implement all necessary utility improvements, including provisions for monitoring, reporting, and enforcement to ensure the long-term sustainability of water and infrastructure resources. (i) No building permit shall be issued until the county has received written confirmation from all affected utility providers that adequate service capacity will be available upon project completion and that all reclamation and reuse requirements have been met.