(a) Upon permanent cessation of operation of the primary use on the site—defined as zero electrical load to the primary use for 90 consecutive days, or a total of 180 days over any 365-day period, whichever occurs first—the owner shall notify the county within 30 days of such occurrence. If cessation of operation is caused by an Act of God, repair or removal shall commence within 180 days. (b) Within 12 months of the date of notification to the county, all structures on the site shall be demolished or removed to grade and the site restored to agricultural viability. Soil tests shall be performed, provided to the county, and native grasses or crops shall be replanted per applicable GA EPD guidelines. (c) The board of commissioners may, at its sole discretion, approve an agreement to extend the timeline for compliance with this section for no more than 90 days.