Meriwether County · Zoning Ordinance
Appendix A - ZONING / Article 13 - PLANNED UNIT DEVELOPMENT
Sec. 13.11. Application for schematic development plan approval (application for the PUD zone).
About this text
- As published by Municode, current through 2026-01-12
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
(a) A schematic development plan shall be filed for approval, rejection or modification by the planning commission of all or portions of the area zoned PUD and reflected within the approved site plan, together with the required filing fee. The schematic development plan shall be scaled at one inch equals 50 feet and shall contain, at a minimum, the following:
(1) Boundary survey and identification plat or survey plat;
(2) The use(s) of all buildings and structures within the schematic development plan area, as well as existing uses of adjacent property external to the PUD-zoned area and proposed uses within adjoining PUD-zoned areas;
(3) The locations, heights, approximate dimensions and conceptual architectural elevations of all buildings and structures, and the setbacks and densities and/or square footage thereof;
(4) The locations of points of access to the site and all public and private roads, and pedestrian and bike paths, in accordance with the applicable thoroughfare design standards;
(5) The locations and setbacks of all parking areas;
(6) Existing topography, including:
a. Contour intervals of not more than two feet;
b. One-hundred-year floodplains and floodways, including base flood elevations;
c. Other natural features, such as rock outcropping and scenic views;
d. Utility easements, if any; and
e. Historic buildings, structures or areas.
(7) All landscaped areas, proposed conceptual screen planting, open spaces, plazas, malls, courts, commercial signage standards, community identification signage, recreation and amenity areas;
(8) Proposed phasing or staging plan of development and information relating to such plan's consistency with the provision of public facilities;
(9) A proposed covenant or other form of agreement indicating how the area will be included in any homeowners' association or other organization, and how any open space, community space or amenities located within the area subject to review will be perpetually maintained;
(10) Eight copies of required preliminary plan/plat submittal for review process (18 inches by 24 inches) or of a size acceptable to the Meriwether County Zoning Administrator. All plats and supporting information shall also be submitted to the Meriwether County Zoning Administrator;
(11) Two copies of the previous plat;
(12) Two drawings that inventory all wetlands, all watercourses and impoundments, and floodplain limits;
(13) Two copies of the erosion and sedimentation-control plan;
(14) Two copies of the stormwater management plan;
(15) Two copies of the utility development plan (water, sewer, gas, electrical, telecommunications);
(16) Transportation plan showing the interconnection on the subdivision and its relationship to all adjoining properties;
(17) Required fees;
(18) Project narrative to include a description of the type of project and who it will serve, developer information, contractor information, engineer information, contact information, anticipated start dates, completion dates, phasing description (if applicable), description of utility development plans including main sizes, lift station information, communications deployment plan and schedule, stormwater planning narrative, impact statement describing the project's effects on surrounding transportation, including traffic counts and flows from the proposed project and existing counts, a narrative description of how traffic will be managed and controlled (and calmed) as appropriate for the development, description of green space and public/community space proposed for the project; and
(19) The application must be signed by the owner, developer and engineer (licensed in Georgia with stamp affixed).
(b) The county commissioners shall take action on the application within 90 days after the application is deemed complete.
History
(Ord. No. 2020-04, § 1(Exh. A), 8-25-2020)
Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.