10-3. Application for Building / Development Permit.

About this text

  • As published by Municode, retrieved 2026-11-11
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

All applications for building/development permits, shall be accompanied by two site plans drawn to scale showing the actual dimensions of the lot to be built upon, the size and location of the lot, the number of dwelling units the building is designed to accommodate, the setback lines of the building on the "permit lot", the various easements on the lot and such other information as may be essential for determining whether the provisions of this ordinance are being observed. Applications shall also include construction documents (building plans) along with any other documentation required by the building/zoning administrator. The following is required on the site plan before the site plan is considered by the zoning administrator and any permits are approved (single-family residential, duplexes and agricultural buildings, and their accessory uses are excluded from the following items except number 3 below):

1. Topography (MSL) existing and proposed;

2. Drainage plans;

3. Location and size of ingress/egress;

4. Water and sewer mains and services, both existing and proposed;

5. Water services as well as fire hydrants in the lot and the specific meter size and location.

Any building/development permit shall become void if the work involved has not begun within six months after the date of issuance of the permit or if the work or development authorized by such permit is suspended or abandoned for a period of six months after the work or development is commenced; provided that extensions of time and periods not exceeding six months each may be allowed in writing by the zoning administrator. Any unapproved deviation from the site plan shall cause the zoning administrator to not issue a certificate of occupancy.

Toilet facilities shall be provided for construction workers, and such facilities shall be maintained in a sanitary condition, that conforms to ANSI Z43.

Building sites and/or work sites must have a dumpster on site (either city furnished, at owner's expense, or by private company), and the site must be maintained in a clean manner.

The applicant for a building permit shall submit a certificate with his application which certifies that the lot which he proposes to develop is a lot of record. When the lot in question does not meet the lot width and lot area requirements of this ordinance, then the applicant shall certify that such lot was a lot of record prior to the adoption of this ordinance or is a lot which has been created through governmental taking of property. In such case, the applicant shall file a copy of the recorded deed showing the date that the property was transferred and the deed recorded, or, in the case of condemnation, the easement or order of taking and survey showing the date and scope of the taking. All applications for a building/development permit shall be closely coordinated with City of Millen's Soil and Sedimentation and Erosion Control Ordinance.

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:millen/zoning/10-3@2026-11-11-7098790856

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Millen Zoning Ordinance, 10-3. Application for Building / Development Permit | Georgia Commons