Mitchell County · Zoning Ordinance
Appendix A - ZONING / Article XI - AG AGRICULTURAL DISTRICT
Sec. 11.06. Solar farms/facilities development standards and general requirements.
About this text
- As published by Municode, current through 2023-08-08
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
Solar farms/facilities shall meet the following requirements:
A. Design standards.
1. Site plan.
a. An engineered site plan depicting the proposed equipment, fencing, protective screening, and setbacks required under this subsection must be submitted at a scale of no less than 1" = 200' with the building permit application. The engineered site plan must also include a vicinity map at a scale of not less than 1" = 600', a north arrow, graphic, and numeric scale, and the total acreage for the project.
2. Equipment.
a. Free standing solar panels or solar arrays shall not exceed eight feet in height as measured from the grade at the base of each structure to the highest point.
b. Mounted solar panels or solar arrays shall not exceed eight feet above the apex of each structure on which it is mounted or the maximum height for building in an agricultural district.
3. Fencing.
a. A minimum height of six feet chain link fencing shall surround the entire solar farm/facility project.
4. Protective screening.
a. A protective screening buffer of evergreen vegetation shall be existing or installed outside the required fencing with a minimum height necessary to not allow visibility of the solar panels or solar arrays from any adjacent roads or rights-of-way.
b. The required evergreen vegetation shall be a minimum height of eight feet with 75 percent opacity at the time of installation and shall reach 100 percent opacity within three years of installation.
c. The required evergreen vegetation must be maintained in a manner to continuously provide the required buffer of proactive screening from any adjacent roads or rights-of-way. If any portion of the evergreen vegetation dies or no longer provides the required screening, replacement vegetation shall be installed. The buffer shall be maintained throughout the entire life of the project.
d. A complete landscape plan, including the protective screening required under this subsection, shall be submitted with the building permit application.
5. Setbacks.
a. Setbacks of 40 feet in all directions shall be required where all adjacent properties are in an agricultural district and there are no residential dwellings on the adjacent properties.
b. Setbacks of 150 feet shall be required from any existing residential dwelling or recreational facility on any adjacent properties.
c. The required setbacks shall be measured from the fencing required under section 11.06(A)(3) to the closest solar panel in each direction.
B. Road restoration bond.
1. A road restoration bond shall be required with a minimum amount of $20,000.00.
2. The road restoration bond shall be maintained for at least three years after completion of the project construction.
C. Erosion control plan.
1. An erosion control plan that complies with all state and local requirements shall be submitted.
D. Decommission plan.
1. A decommission plan shall be submitted with the building permit application in a form suitable to the building official.
2. The decommission plan shall cover the anticipated service life of the solar farm/facility and for any abandonment of the project.
3. A performance guarantee shall be submitted in the form of a bond, irrevocable letter of credit and agreement, or other acceptable financial security in the amount of 125 percent of the estimated decommission costs, minus any salvage value or $50,000.00, whichever is greater. The estimates shall be provided by an engineer licensed to practice in the State of Georgia and agreed upon by the building official.
E. Ground water testing.
1. A minimum of at least one 20-foot ground water monitoring well shall be installed for each project as determined by the building official.
2. The required well shall be tested for the presence of any heavy metals. After initial testing, a biannual test shall be required for two testing periods. If no contaminants are identified in the first two testing periods, testing may shift to a five-year schedule. The well also shall be tested prior to any decommissioning.
F. Maintenance.
1. All grass shall be maintained in a manner to mitigate fire hazards at all times.
2. Mounted solar panels or solar arrays shall be spaced in a manner to allow county fire-rescue to operate safely within the entire solar farm/facility, or the applicant shall provide county fire-rescue the necessary fire suppression equipment capable of operating in a safe manner within the soar farm/facility that is deemed suitable by the building official.
G. Vendor registration.
1. A list of vendors capable of removing construction materials or scraps from the project shall be submitted to the building official.
2. Any change to the vendor list shall be provided to the building official when such change occurs.
History
(Ord. No. 2023-004, § 2, 8-8-2023)
Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.