A. Zoning Compliance Permit. No building, structure or sign shall be erected, altered, or moved, and no use shall be commenced, unless a zoning compliance permit has been issued by the zoning administrator prior to commencing that work or use.

1. Except upon approval of a variance by the zoning board of appeals or upon the order of a court of competent jurisdiction, no zoning compliance permit shall be issued for the erection, alteration, or use of any building or structure, or for the use of any land which is not in accordance with all provisions of this ordinance and any conditions of approval imposed on the particular building, structure or use.

2. A record of all zoning compliance certificates shall be kept on file in the office of the zoning administrator.

3. No vacant land shall be used and no existing use of land or buildings shall be changed to a different class of use, nor shall there be any change that results in an increase in parking space requirements, unless a zoning compliance permit is first obtained for the new or changed use.

B. Certificate of Occupancy. No building or structure erected or altered after the date of adoption of this ordinance shall be occupied or used unless and until a certificate of occupancy has been issued for that building or structure upon completion of construction. A certificate of occupancy shall constitute certification that the building, structure, use, parking, landscaping and all other required improvements fully comply with the applicable provisions of the zoning ordinance and any conditions of approval that may have been imposed by the city.

C. Land Disturbance Permit. No clearing, grubbing, excavating, filling, grading or other land disturbance activities shall occur on a site or portion of a site unless and until a land disturbance permit has been issued.

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:palmetto/zoning/21-2@2026-11-11-b252bc5771

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Palmetto Zoning Ordinance, Sec. 21-2. Permits and procedures | Georgia Commons