Sec. 403. Preliminary plat approval process.

About this text

  • As published by Municode, retrieved 2026-11-14
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

The preliminary plat shall not be accepted for review until after the concept plat is approved by city staff and the planning commission. The city planner shall be responsible for administering the preliminary plat review and approval process.

Application for preliminary plat approval shall be made directly to the city planner and shall include, at a minimum, the following:

(a) Applicable review fee.

(b) Six full size copies of the preliminary plat, which shall meet the specifications contained within section 502 of these regulations.

(c) Electronic copy (pdf format) of entire submittal package.

(d) The city planner shall review the preliminary plat submittal within three business days of receipt to ensure compliance with the approved concept plat and the submittal requirements identified herein.

(1) If the concept plat does not meet these requirements, the plat shall be returned to the applicant for corrections. A resubmittal fee shall be required when the revised plat is submitted.

(2) If the concept plat meets these requirements, the city planner shall distribute the plat and supporting documentation to appropriate city staff for review and comment.

(e) City staff shall have 20 business days, excluding weekends and holidays, from the date a complete application is submitted to review the application and return comments to the city planner. The city planner shall assemble these comments and forward them to the applicant.

(f) If revisions are necessary, three copies of the revised preliminary plat and a revised 11" × 17" reduction shall be submitted to the city planner, at which time it will be date stamped as received. A resubmittal fee shall be required when the revised plat is submitted.

(g) Once the preliminary plat is ready to be approved, the plat shall be signed by the city planner and the planning commission representative. The city planner shall distribute copies of the approved preliminary plat to the applicant, city engineer and the development inspector.

(h) Approval of a preliminary plat shall expire 12 months from the date of approval if construction plans are not submitted to the city planner.

History

The history line the source prints at the end of the section.

(Ord. No. 972, § 1, 4-16-2009)

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:peachtree-city/zoning/403@2026-11-14-9f8f95d810

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Peachtree City Zoning Ordinance, Sec. 403. Preliminary plat approval process | Georgia Commons