6-5. Water supply and sanitary sewerage.

About this text

  • As published by Municode, current through 2025-01-07
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

6-5.1 Provision of facilities. The subdivider shall provide every lot of a proposed subdivision with adequate water and sanitary sewer facilities in accordance with all applicable state and local regulations. Where existing water and/or sewer mains are in the street, but no services to the proposed lots exist, the subdivider shall arrange to have the services installed. Said facilities are to be dedicated to the local government for public maintenance and operations prior to the recording of the final plat. The entire cost of extending water and sewer lines and their associated services within the subdivision shall be borne by the developer.

6-5.2 Private water and sanitary systems. In subdivisions that are not to be served by a public water and/or sewer system, the subdivider shall either arrange for the provision of water and sanitary sewer service via a private system, or shall arrange for the provision of well water and on-site septic systems. Well water and septic tanks shall not be installed without first obtaining all applicable permits.

6-5.3 Well water. New lots that are created outside of a public water service area must either be within the service area of a private water system, or must meet all size requirements, setback limits, and other requirements for the provision of an on-site well for water service. No lot shall be created outside of a public or private water service area that does not meet all state and local requirements for well permitting.

6-5.4 Septic tanks. New lots that are created outside of a public sanitary sewer service area must either be within the service area of a private sewer system, or must meet all size requirements, setback limits, and other requirements for the provision of on-site septic facilities. No lot shall be created outside of a public or private sewer service area that does not meet all state and local requirements for septic tank permitting.

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:pierce-county/zoning/6-5@2025-01-07-6fff04f9d8

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Pierce County Zoning Ordinance, 6-5. Water supply and sanitary sewerage | Georgia Commons