The requirements of this section shall apply to every major subdivision and site development and shall be planned for and provided by the developer by installation and/or payment prior to the approval of the final plat. Where indicated by an asterisk (*), the requirement is not necessarily applicable to a site development as shall be determined by the director in consultation with the developer.
(a) * Street names. All streets shall be named and marked with MUTCD signs. Street names shall have the approval of the director and shall not duplicate, nor closely approximate phonetically or visually, the name of any other street in the county. A street that is in alignment with an existing street shall continue the name of the existing street.
(b) Streets. All streets, whether public, private or curb cuts, shall be designed, constructed and paved in accordance with the standards set forth in this chapter.
(1) No street or drainage structure shall be accepted by the county until it shall have been in public use for two years (two-year warranty period) and all repairs required by the county have been completed to the satisfaction of the county.
(2) To initiate the two-year warranty period the county must conduct an inspection of all drainage structures, the road, grading, grassing, and the use of best management practices for soil and erosion control. The developer/owner must post a surety or cash bond per section 28-82 of this chapter.
(3) It is the responsibility of the developer to maintain all streets until they are accepted by the county, and issue a surety bond to the county, to provide for such maintenance and repair, should the developer not be able to conduct the required repairs, as provided by this chapter.
(4) The developer shall install all necessary traffic control signs, signals, and street name signs as required by the county or GDOT at its sole cost. In addition, the subdivider shall provide suitable ground cover, such as grass, on all unpaved areas of street right-of-way or other public areas. All grassing shall be done to DOT specifications.
(5) If at the end of the two-year warranty period the road or drainage structures are not in good maintenance, the county will require the developer/owner to make such repairs to bring the road or drainage structures into good maintenance. If after 60 days notice from the county the developer/owner has not made the required repairs, the county may seek to call the bond or other surety.
(c) Utilities.
(1) Generally. All water, sewer, natural gas lines and hydrants shall be along street rights-of-way. The water, sewer and natural gas lines shall be underground and located on back slopes of rights-of-way across drainage ditches away from pavements in order to prevent damage to the pavement during utility construction or maintenance. Only gravity-fed sewer lines may be placed under the pavement. Where required, because of topography, location of existing utilities or other factors, the director may allow the installation of utilities in other areas; however, the alternate location must be shown on the construction drawings and the as-built survey. Water and sewer lines must be on opposite sides of the street. Underground power lines must be located above and four feet to the side of either a water or sewer line.
(2) Water. If a public or private water system is proposed to service the area of the subdivision within two years of the approval of the subdivision, water mains shall be installed by the subdivider within the subdivision with connections to each lot in each phase extended to the lot lines. If a public water system is available within 1,000 feet of either a residential or commercial development, a hookup to such is required. If a public or private water system is not available, the subdivider shall provide a water supply through a community water system or individual wells in conformity with the regulations of the county health department and this chapter.
(3) Sewer. If a public sanitary sewer system is proposed to service the area of the subdivision within two years of the approval of the subdivision, sewer mains shall be installed by the subdivider within the subdivision with connections to each lot in each phase extended to the lot line. If a public sewer system is not available, the subdivider shall provide a community sewage collection and treatment system or individual septic tank systems in conformity with the regulations of the county health department and the state department of natural resources.
(4) Fire hydrants (see chapter 32-19 of the Putnam County Code of Ordinances).
(d) Storm drainage.
(1) Design. Lots shall be laid out so as to provide positive drainage away from all buildings, and lot drainage patterns for the area. Drainage shall be designed so as to avoid concentration of storm drainage water from each lot to adjacent lots and any drainage feature must be capable of handling a 25-year storm event.
Sensitive or high-risk areas will require handling larger storm events, which will be the responsibility of the designing engineer. Multifamily, commercial and industrial developments must take particular care in the design of the parking facilities and buildings with respect to the amount and direction of the runoff.
(2) Design certification. A professional engineer must certify that the proposed storm drainage improvements and other proposed construction is adequate, complies with the requirements of this chapter, and complies with accepted engineering practice.
(3) Connection to existing systems. If a storm system is located reasonably near the proposed development or subdivision, then the development or subdivision must contain an underground storm drainage system, which will be connected to the existing system. Should a storm drainage system not exist then adequate surface drainage facilities shall be installed. The professional engineer must ensure that the existing system is capable of accepting the additional stormwater without surcharging or damaging the existing system.
(4) Stormwater management. Stormwater detention facilities or other forms of suitable storage features will be required where more than a five-percent increase in runoff occurs between the calculated pre-developed flows and the calculated post-developed flows. In addition, detention/retention facilities shall be required if the downstream facilities are not adequate to allow increased runoff. If the facility is deemed to be inadequate, the developer can request permission to modify (at his expense) the downstream facilities to allow a reduction in detention facilities as long as no downstream facilities or lands of others are harmed by the change. The maximum predevelopment rational method runoff coefficient ("C" factor) to be utilized while calculating flows shall be 0.25 for flat and rolling terrain and 0.30 for hilly (seven percent plus) terrain.
Post development "C" factors to be utilized shall be related to the density of the development and amount of impervious area included in the development. All "C" factors shall be in accordance with accepted Rational Method Runoff Tables published. Calculations utilizing the Soil Conservation Service (SCS) method of determining the runoff shall utilize the SCS soil group tables and covering to determine the SCS CN number to be used in the calculations. Calculations shall be shown for the two-, five-, ten-, and 25-year storm events. Emergency spillways shall be sized to handle a 100-year storm event. For pre-developed flows, the time of concentration (TOC) shall not be less than five minutes.
(5) Roadside ditches. Front and back slopes for roadside ditches shall be 3:1 or flatter. Ditches shall be designed to handle at least a 25-year storm event and velocities within the ditch are recommended to be held below two feet per second. Velocities above two feet per second will require additional stabilization practices. Erosion matting meeting DOT specifications is recommended and may be required within any ditch. Check dams or other suitable structures shall be placed in accordance with the Manual for Erosion and Sediment Control in Georgia, latest edition.
(6) Drainage structures. Where drainage pipes, curb inlets, junction boxes, headwalls, and other structures are utilized, these shall conform to the Georgia DOT Standard Detail Manual, latest edition.
(7) Curb and gutter. Curb and gutter meeting Georgia DOT Standard Detail Manual specifications is recommended for any new development. In residential areas, curb and gutter may either be 18 to 24-inch standup ("L" backing) or rollback type. In commercial and industrial areas, 30-inch standup is required.
Associated junction boxes, piping, transitions, and other appurtenances shall meet Georgia DOT specifications.
(e) Development along arterial or collector streets. Where a subdivision abuts or contains an arterial or collector street or railroad right-of-way the following are required:
(1) In a village, commercial or industrial-manufacturing zoning district of ten acres or more, the following shall apply: a two-lane access road parallel to the arterial or collector, separated from the arterial or collector by a ten-foot wide landscaped strip through which access shall be provided at intervals of no less than 500 feet or whenever coincident with a median break should one exist in the arterial or collector street shall be required.
(2) In residential zoning districts (including multifamily), a 20-foot wide nonaccess buffer along the entire length of the back of the lots abutting an arterial or collector street is required.
(3) Setbacks from arterial roads: 50 feet.
(f) Lot sizes. All lots shall conform to the Putnam County Zoning Ordinance. The arrangement of the subdivision lots and design of the development and the required improvements, however, are controlled by this chapter.
(g) * Lot lines. All subdivision side lot lines shall be perpendicular or radial to street lines, unless otherwise approved by the director in furtherance of creative design models.
(h) * Double and reverse frontage lots. Double frontage and reverse frontage lots shall be required to provide separation of development from an arterial street or to overcome specific disadvantages of topography and orientation.
(i) Easements. The director of the planning and development department may require easements having an adequate width and located along rear and/or side lot lines for utility lines, drainage and underground cables, with provision for access from a public way. The director may also require access easements to existing parcels not otherwise fronting on a public road.
(j) Reserve strips. Reserve strips that control access to street and public grounds shall be permitted only when the reserve strip is deeded to the county.
(k) Deceleration lanes and center turn lanes.
(1) Deceleration lanes or a center turn lane are required if sight distances required by this chapter cannot be achieved or the number of dwelling units in a development exceeds 50, at each entrance to a multifamily or nonresidential development project intersecting a county collector or a county arterial road, or if the director deems either a deceleration or turn lane or both are necessary to protect the safety of the public.
(2) Deceleration and turn lane construction standards.
a. Deceleration lanes shall be designed and installed in accordance with the Georgia Department of Transportation Regulations for Driveway and Encroachment Control. The lane shall be 12 feet in width exclusive of the curb and gutter width. Additional right-of-way to accommodate the deceleration lane and a ten-foot shoulder shall be dedicated by the developer to the county.
b. Left turn lanes may be required if the average daily traffic (ADT) exceeds 2,000 vehicles per day or if the director has knowledge of other information that would warrant a detailed traffic impact study as established by the Georgia Department of Transportation to determine if a left turn is needed. The study shall be prepared in accordance with the Georgia Department of Transportation Regulations for Driveway and Encroachment Control.
c. Other project access improvements as deemed necessary by the director of the planning and development department in addition to a required deceleration lane in order to ensure adequate site access, pedestrian access, convenience, and safety to the motoring public may be required.
(l) Minimum water main sizes. To allow for fire protection, all plans for development must meet all applicable fire protection codes. All water mains servicing any development shall be no less than eight inches in diameter.
History
(Res. of 7-17-2007(2); Ord. of 3-15-2016(1); Ord. of 7-19-2022(1))
Meetings that refer to this section