Sec. 67-32. Requirements of submissions.

About this text

  • As published by Municode, retrieved 2026-11-11
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

(1) The coverage plan:

a. A basic condition of the city tree management plan is that all applicable sites maintain a minimum tree canopy of 40 percent. Trees may be tiered and grouped with understory trees planted under the over-story shade canopy of a new or existing tree.

Total canopy coverage shall be computed from sum of the understory and overstory trees planted and existing.

b. The tree management plan will be reviewed concurrently with the preliminary plat or site plan, as the case may be. The developer is responsible for developing and submitting the tree management plan and the plan shall be based on the gross area to be developed. Once the developer sells individual lots, the builder/owner is responsible for implementing the plan for the lots purchased. Once a certificate of occupancy has been issued, this chapter ceases to be in force for that lot or property.

c. The canopy requirement must be met whether or not a site had trees prior to development or disturbance of the applicable site. The canopy may be achieved by preserving existing trees, by planting new trees according to the minimum standards in this chapter or by a combination of the two. Minimum tree canopy shall be calculated and established pursuant to the formula and analysis set forth in appendix A to this chapter, and the engineering design standards of the city. Any existing tree of not less than six inches DBH left in good growing condition on the property is eligible to be counted toward the minimum required canopy and must be protected as provided in the city engineering standards to qualify to be counted. The developer shall be subject to the minimum tree canopy requirement set forth in this section. Fifty percent of the canopy coverage in wetlands may be utilized to satisfy the canopy coverage requirements, provided that such wetlands are under the same ownership, and included within the same project or development. If canopy coverage in wetlands meets the 40 percent gross canopy coverage required by the tree plan, developer/builder shall, nonetheless, be required, under any circumstances, to plant a minimum of one tree per residential lot with two-inch DBH. The developer shall base the canopy calculation on the gross site area, and with each such calculation, shall furnish a statement of ownership covering all of the lands on which trees are located that were included in the minimum canopy.

d. Trees planted to achieve canopy requirements are to be selected species from the city tree species selection list - appendix E (which list values of canopy coverage in square feet for various groups of trees and minimum areas for planting), on file with the city.

Any species indigenous to the city, and not on the prohibited species list, as shown in appendix B, can be selected for planting even though it may not be included in appendix E. In addition, planting shall be at the ratio of not less than one overstory tree for every three understory trees. Canopy credit may be met by planting all overstory trees, but not by planting only understory trees. No more than 40 percent of any one genus may be included in any planting plan. All trees will be maintained properly by the builder or developer to ensure their survivability until a certificate of occupancy is issued. In the case of a common area, the builder or developer will retain responsibility for maintenance as provided in [article VI] of this chapter. All residential lots shall have at least one tree planted or existing.

e. In order to promote diversity, no more than 15 percent of the replacement trees shall be of the same species.

(2) The protection plan:

a. The tree protection plan shall be a detailed plan designed by a certified arborist, landscape architect or civil engineer to protect and preserve trees before, during and for a period of three years after planting or protection on any unsold lot or of any required project improvements. Any trees designated for retention by the tree protection plan located on any unsold lot or required project improvement that die or are damaged within the first three years after planting or protection shall be replaced in accordance with this chapter. The developer is only responsible for maintenance of trees located on property not yet sold. All trees shall be maintained for a minimum of three consecutive years after planting or replacement or until such time as a certificate of occupancy is issued, whichever shall first occur. Trees retained and planted in common areas shall be maintained by the developer until the sooner of the end of the three-year maintenance period, or the developer passes title and surrenders control of the common areas as provided in [article VI] of this chapter. A certificate of occupancy for residential property will not be issued if the lot upon which the structure sits does not meet the requirements of at least one tree (two-inch dbh) tree per lot.

b. Tree protection barriers shall be erected around all existing trees and/or groupings to be preserved to meet standards set by the International Society of Arboriculture, Georgia Forestry Commission, and the city's requirements for protection of street trees or other trees required by city tree plan. (See appendix D)

(3) The planting plan:

a. The planting plan shall consist of a schedule setting forth the time or times when all required protective devices will be installed on all preserved trees and the date or dates of planting of all trees to be planted on the site.

b. The planting plan shall also contain a good faith estimate of the cost of all such protective devices and plantings.

(4) The bond (if required):

a. When the tree board shall determine it in the best interest of the city, as well as the project involved, to allow a developer to receive subdivision approval, as well as final plat approval, prior to fully complying with the developmental regulations of this chapter, or when the board shall find that for reasons beyond the control of a developer, the developer has been providentially delayed or prevented from timely compliance with the developmental regulations of this chapter, the board may recommend, and council may approve, such permits and approvals provided that the developer post a bond or cash deposit for such improvements in an amount recommended by the tree board, after receiving the advice of the city arborist and approved by council, and further provided that, regardless of any bond, all such plantings, protective devices and other required improvements must be fully completed within one year of the issuance of final plat approval of any residential subdivision or the final approval phase of any other development.

b. In determining whether or not the tree board shall recommend allowing such required improvements to be bonded and a developer to receive approvals prior to the completion of the same, and in determining whether or not city council shall allow such, both the tree board and city council shall be guided by the following criteria:

1. The amount and nature of the required improvements.

2. The cost of the required improvements.

3. The nature and complexity of the work involved.

4. The reason or reasons that the improvements have not or cannot be completed prior to the developer's receipt of approvals.

5. Any unusual weather conditions.

6. Any unusual conditions on the land.

7. Any difficulties in obtaining labor or supplies.

8. Any other providential reason for such delay.

c. In setting such amount, both the tree board and city council shall be guided by the following criteria:

1. The estimated cost of the improvements.

2. The size of the subdivision.

3. The schedule within which the improvements are to be completed.

4. The availability of prospective contractors for the construction of the improvements.

5. The cost involved to put the construction or completion of the improvements to bid.

6. The cost involved for supervising the construction or completion of the improvements.

7. The degree to which the improvements are actually completed.

d. The bond or cash deposit shall be in such form and upon such forms as the tree board may require and shall be in an amount as set by council with sureties and conditions attached satisfactory to city council, providing for and securing the city for such a period of time as specified by city council and expressed in the bond or cash deposit, in such an amount of money as set by city council to ensure the satisfactory completion of the required improvements.

e. Upon such bond or cash deposit being approved and filed, the city shall have the power to enforce the same by all appropriate legal and equitable remedies.

f. Upon the completion of all plantings and improvements secured by a planting bond, the developer or other responsible person shall make application to city council for an inspection of the required improvements. Such application shall be upon forms specified by the planning commission, who shall cause an inspection of the plantings and improvements to be made, and if the same are found not to be up to the specifications as required by this chapter and the city engineering standards, the developer or other responsible person shall be notified in writing of such deficiencies.

After correction of any deficiencies, the developer or other responsible shall again offer the plantings and improvements for inspection. If there are no deficiencies found, the city shall notify the developer or other responsible person and shall release the entirety of the planting bond.

g. All plantings, protective devices and other required improvements shall be fully installed and completed within one year of final plat approval in the case of a residential development or the final approval phase of any other development.

(5) The maintenance plan: The maintenance plan shall consist of a written narrative describing how, when and by whom the tree protection plan will be carried out and a bond to insure compliance with said tree protection plan.

a. The tree board shall, with the advice of the city arborist, determine the amount of the bond, which shall in no event be less than ten percent of the amount of the estimated cost of the improvements.

b. Said bond may be properly posted by either a cash deposit or the posting of a bond with sureties and conditions attached satisfactory to the tree board and providing for and securing to the city for a period of three years after final inspection of the improvements required under this chapter in such an amount of money as set by the tree board to ensure the satisfactory maintenance and upkeep of all such improvements for said three-year period.

c. In determining the amount of such bond or cash deposit, the tree board shall be guided by the following criteria:

1. The estimated cost of the improvements.

2. The size of the subdivision.

3. The availability of prospective contractors for the construction of the improvements.

4. The cost involved to put the construction or completion of the improvements to bid.

5. The cost involved for supervising the construction or completion of the improvements.

6. The current condition of the improvements.

d. Upon such bond or cash deposit being approved and filed, the city shall have the power to enforce the same by all appropriate legal and equitable remedies.

e. One year after acceptance of the tree maintenance plan and final inspection of the required improvements under this chapter, the developer or other responsible person may make application to the city council for a second inspection of the required improvements. Such application shall be upon forms specified by the planning commission, who shall cause a second inspection of the improvements to be made, and if the same are found not to be maintained up to specifications as required by this chapter and the city engineering standards, the developer or other responsible person shall be notified in writing of such deficiencies. After correction of any deficiencies, the developer or other responsible person shall again offer the improvements for inspection. If there are no deficiencies found, the city shall notify the developer or other responsible person and shall release 20 percent of developer's, or other responsible person's, bond or cash deposit.

f. Two years after the acceptance of the tree maintenance plan and final inspection of the required improvements under this chapter, the developer or other responsible person may request in writing an additional inspection of the improvements, and if the improvements are found not to be maintained up to specifications as required by this chapter and the city engineering standards, the developer or other responsible person shall be notified in writing of such deficiencies. After correction of any deficiencies, the developer or other responsible person shall notify the city of such corrections and offer the improvements for inspection. If there are no deficiencies found, the city shall notify the developer or other responsible person and shall release an additional 20 percent of the developer's, or other responsible person's, bond or cash deposit.

g. Three years after the acceptance of the tree maintenance plan and final inspection of the required improvements under this chapter, the developer or other responsible person may request in writing an additional inspection of the improvements, and if the improvements are found not to be maintained up to specifications as required by this chapter and the city engineering standards, the developer or other responsible person shall be notified in writing of such deficiencies. After correction of any deficiencies, the developer or other responsible person shall notify the city of such corrections and offer the improvements for inspection. If there are no deficiencies found, the city shall notify the developer or other responsible person and shall release the balance of the developer's, or other responsible person's, bond or cash deposit.

h. In the event that a developer or builder shall transfer title to the common areas of any project or lands subject to this chapter to the owner or a property owner's or similar association under the provisions of [article VI] of this chapter prior to the expiration of the three-year maintenance period, the developer or builder shall not be relieved of his/her/its responsibilities under any maintenance bond, nor entitled to the release of any portion of any maintenance bond as a result of such transfer, unless the receiving owner or association shall post a new maintenance bond in the amount of the unreleased balance of said original maintenance bond. Alternatively, any developer or other responsible person transferring title to the common areas of any project or lands subject to the this chapter to an owner or property owner's or similar association under the provisions of [article VI] of this chapter may assign, in writing, the unreleased portion of the subject maintenance bond to the owner, property owner's or similar association, accepting such common areas by means of a writing, filed with the tree board.

History

The history line the source prints at the end of the section.

(Ord. of 7-7-10, (ch. 3, § 2))

Meetings that refer to this section

Found 1: meetings of this government whose minutes or machine transcripts name this section, or an ordinance in its history line, newest first. Found by rule from those records' own words. A reference is a pointer to another record, not a statement that the section applies or was changed.

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:richmond-hill/code/67-32@2026-11-11-3e2ab32959

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Richmond Hill Code of Ordinances, Sec. 67-32. Requirements of submissions | Georgia Commons