Sec. 302-24. Site development plans.

About this text

  • As published by Municode, current through 2026-01-27
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

(a) Applicability. Site developments consist of proposed developments of a single parcel of land, having a single phase, other than a one- or two-family dwelling or a residential accessory structure, that do not require subdivision of property into separate lots or units for sale.

(b) Process. Site development plans shall be subject to the application, review and approval procedures of this section, consisting of the preparation and approval of a site development plan and construction plans for site development and

public improvements.

(c) Site development plan application.

(1) Prior to undertaking disturbance of land or construction requiring a building permit, the developer shall submit to the department a site development plan and

an application on a form provided by the department. The application for approval of a site development plan shall be accompanied by the required fee and the following information:

a. A natural resources plan, if the site is larger than one acre and has not been developed previously for commercial use or is a recorded lot in a commercial subdivision. The natural

resources plan shall include a map drawn at one inch = 100 feet that indicates the presence of streams, lakes, floodplain, wetlands, prime vegetation, endangered species, steep slopes, shallow or exposed rock or

other site resources or site hazards and the appropriate protection or mitigation measures that will be taken in development of the site.

b. A traffic impact study for developments that exceed the thresholds published by GRTA, or have trip

generation greater than 2,000 daily trips, whichever is less, prepared in accordance with the standards and requirements of GRTA, or the Institute of Transportation Engineers.

(2) The site development plan shall provide all elements required in section 302-62.

(d) Site development plan review.

(1) If the application is certified as complete, the director shall review the site development plan with respect to its consistency with the Rockdale County Comprehensive plan and conformity with each of the standards and requirements of this section and all other applicable sections of the UDO.

(2) Concurrent with review of the site development plan, the director shall review the natural resources plan and traffic impact

study, if required. Such review shall assess the conformity with each of the standards and requirements of this chapter, chapter 332 and chapter 222.

(3) If the natural resources plan or traffic impact study is disapproved, the applicant shall revise and resubmit such document so that it meets the standards of this section and addresses the reasons for

disapproval in a manner that is satisfactory to the director.

( 4) The director shall coordinate the internal review of all site development plans and related documents with staff members representing the disciplines of planning, zoning, transportation, stormwater, general engineering, GIS, water/sewer, environmental health, the Rockdale County Department of Communications, county

arborist/urban forester and the fire marshal. The director shall have final staff authority to determine the applicability of

any and all comments of staff and review agencies under these regulations or conditions of zoning approval.

(5) Approval of the site development plan shall be contingent on the director's approval of the natural resources plan and traffic impact study, if applicable.

(6) The director shall indicate on a review copy of the drawings or in a memorandum, all comments related to compliance of the site development plan with the

comprehensive plan, this UDO, principles of good engineering and design, conditions of zoning approval and regulations of other county departments and state

agencies as appropriate.

(7) The director shall have no more than 60 days either to approve or disapprove the site development plan. If the director disapproves of the application, the director shall notify the applicant in writing, stating the reasons. If approved, such action shall be noted on two copies of the site

development plan. One copy shall be returned to the applicant, and the other copy shall be retained and made a part of

the department's records.

(8) The applicant shall be responsible for compliance with all federal, state and local codes, regulations and zoning requirements and for the satisfaction of all of the noted and written comments of the department and related agencies reviewing the site development plan.

(e) Resubmission. If the site development plan is not approved, the applicant shall resubmit ten copies of the site development plan and completed application form correcting all deficiencies, along with the appropriate resubmission fee. Failure to resubmit the site development plan within 180 days shall void the application and require the applicant to submit a new application for site development plan approval with appropriate fees.

(f) Effect of approval.

(1) Approval of the site development plan shall be deemed an expression of approval of the layout of the development to be used as a guide to the preparation of construction plans.

(2) The approval of the site development plan shall expire if a land disturbance permit for any required improvements has not been issued within 12 months of the date of approval of the site development plan.

(3) Approval of the site development plan shall entitle the applicant to prepare and submit construction plans for site improvements required in this section in conformity with article IV of this chapter and other provisions of the UDO (g), Land

disturbance permits.

Following approval of construction plans for site developments and required improvements, a land disturbance permit to construct the required improvements for a site development may be issued at the applicant's request. See also section 302-46.

(h) Development conformance for site developments.

(1) After completion of the construction of any required improvements for all or part of the area shown on the approved site development plan and before seeking a building permit, the developer shall submit all required certificates, including certification for stormwater management facilities, and guarantees and sureties for required improvements not yet completed,

as provided in section 302-28, to the department for approval. The applicant also shall provide copies of the site development plan to all utility companies serving the area.

(2) All improvements and utility installations that are required for approval that are to be dedicated under the rules and

regulations of the county shall be completed in accordance with the appropriate specifications, unless the applicant provides guarantees and sureties for required improvements not yet completed in accordance with the performance and

maintenance agreement, as provided in section 302-28.

(3) The director shall certify by signature on the original of the site development plan that all of the requirements of this UDO, and the conditions of zoning approval, if any, have been met, and that all other affected departments and agencies have inspected and approved the construction of improvements pursuant to the approved site development plan.

History

The history line the source prints at the end of the section.

(Ord. No. 0-2006-32, §§ 1-3, 11-28-2006)

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:rockdale-county/zoning/302-24@2026-01-27-35741402d6

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Rockdale County Zoning Ordinance, Sec. 302-24. Site development plans | Georgia Commons