Sec. 302-34. Construction plans.

About this text

  • As published by Municode, current through 2026-01-27
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

(a) Authority.

(1) Following approval of the preliminary plat or site development plan, the applicant shall submit an application for approval of construction plans to the department for all site development and improvements.

(2) No permit for development or construction activity requiring a preliminary plat, site development plan, or construction

plans shall be issued prior to approval of construction plans.

(b) Application.

(1) The applicant for construction plans approval shall submit an application, accompanied by the appropriate fees, and the required number of construction plans

and related documentation, including, but not limited to following elements:

a. Stormwater management plan-See chapter 310.

b. Soil erosion and sedimentation control plan-See subsection 306-5(c).

c. Buffer plan and tree protection and replacement plan-See section 302- 63.

d. Grading plan-See section 302-64.

e. Streets, sidewalks and bicycle improvements plan-See section 302- 65.

f. Water supply plan-See chapter 98, article II.

g. Wastewater system plan-See chapter 98, article III.

(2) All construction drawings and other engineering data, except the, buffer plan and landscape plan, shall be prepared, signed

and sealed by a professional engineer currently registered in the State of Georgia, in accordance with the provisions of Georgia law.

(3) The buffer plan and tree protection and replacement plan shall be prepared, signed, and sealed by a professional engineer (PE) or registered landscape architect licensed in the State of Georgia, in accordance with the provisions of Georgia Law.

( 4) Multi-phase developments may submit construction plans in phases, provided they are consistent with the approved concept

plan and/or preliminary plat for the entire project.

(5) After receiving an application for approval of construction plans, the director shall determine whether the application

is complete or insufficient. If the application is determined to be incomplete or insufficient, the director shall notify the

applicant in writing and shall require that the application for construction plans approval be resubmitted, along with appropriate resubmission fees, prior to further review.

(c) Review of construction plans.

(1) The director shall review construction plans prepared pursuant to this section, with respect to their consistency with the Rockdale County Comprehensive Plan, the preliminary plat or site development plan and the conformity of the construction plans with each of the standards and requirements of this section and all other applicable sections of the UDO. The applicant shall be responsible for compliance with all state and federal codes and regulations and generally accepted engineering principles and practices.

(2) Within 20 working days of receipt of the completed application for construction plans approval, the director shall prepare a written report documenting approval or disapproval of the construction plans. This report shall document any conditions of approval, if approved, or reasons for disapproval, if disapproved. If said report is not issued within 20 working days, the

construction plans shall be deemed approved. The applicant shall be responsible for meeting all zoning requirements and

comments of the director.

(3) If the construction plans are disapproved, the applicant shall resubmit revised construction plans that meet the standards of this section and other applicable provisions of the UDO and address the reasons for disapproval in a manner that is satisfactory to the director. If said applicant fails to resubmit revised construction plans

within 180 days after disapproval, the preliminary plat or site development plan shall be void; and a new preliminary plat or site development plan, as applicable, shall be submitted by the applicant, along with appropriate resubmission fees.

(Ord. No. 0-2006-32, §§ 1-3, 11-28-2006; Ord. No.

0-2007-14, § 16, 7-24-2007)

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:rockdale-county/zoning/302-34@2026-01-27-37991178d9

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Rockdale County Zoning Ordinance, Sec. 302-34. Construction plans | Georgia Commons