a. A development permit shall expire if the development activity described in the permit is not begun within six months from the date of issuance. b. The Chief Building Inspector may renew any development permit that has expired with the concurrence of the respective Public Works Department, within six months of expiration. If a development permit has expired for more than six months, the applicant shall be required to apply for a new development permitunder the development permit approval process of this Development Code. (Ord. No. 01-7-2, § I, 7-16-01; Ord. No. 05-2-4, § I, 2-7-05) 2.6. Flood area permit. 2.6.1. Permit required. If development or construction is proposed within or affecting an area of special flood hazard, approval of a flood area permit application shall be required. An application for a flood area permit may be included with and reviewed as part of a development permit application.