2.9.2. Building inspection.
About this text
- As published by Municode, current through 2026-01-26
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
a. Inspections shall be scheduled with the Chief Building Inspector at least 24 hours before the inspection is needed for all foundations and footings, and 48 hours prior to all other inspections. Requests for inspection should include the street address, lot number, building permit number, and type of inspection.
b. Required Inspections:
(1) Foundation. Verify minimum required building setbacks, footing, trenches dug and reinforcing steel in place.
(2) Plumbing Connections. Water supply line and sewer lateral in slab foundation.
(3) Framing. Completion of all roughins and after insulation is installed.
(4) Interior walls may not be covered until the following inspections are completed:
(a) Mechanical. Rough-ins complete with pressure test on gas line.
(b) Electrical. Rough-ins with neutral, ground, and service cable wired are completed.
(c) Plumbing. Rough-ins complete and all fixtures installed.
(d) Other inspections are completed as required by the Building Inspection Department as necessary to ensure compliance with all applicable codes.
(5) Final Inspection. Building is complete and ready to occupy.