Construction of the storm drainage facilities shall be initiated as part of the grading of the site and in accordance with the approved stormwater management plan. Stormwater detention facilities shall be constructed prior to the installation of any other site improvements, and may be utilized under proper design as sedimentation basins during development. Installation of all other storm drainage pipes, culverts, headwalls, and ditches, shall be coordinated with the construction of streets and other site improvements, as appropriate. 6.12.4. Earthen embankments. Earthen embankments shall be placed in uniform layers not to exceed a compacted thickness of six inches per layer and shall be compacted to a density of 95 percent of the maximum laboratory dry weight per cubic foot as determined by AASHTO Method T-99 in all areas where structures, parking lots and drives, streets, and utilities are to be placed. All other embankments are to be compacted to at least 90 percent. Proofrolling shall be accomplished prior to placement of embankments to detect soft spots.