6.15.5. Stormwater detention facilities.

About this text

  • As published by Municode, current through 2026-01-26
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

a. Reservoir routing methods shall be used for all detention facility design.

b. The drainage system being developed shall have adequate capacity to bypass through the development the flow from all upstream areas for a storm of 25-year design frequency for the land off site and upstream under existing development.

The 25-year flow rate of record or computed using a runoff coefficient of not less than 0.50.

c. The Public Works Department may permit several developers to construct joint facilities. The Public Works Department shall approve or disapprove the waiver of onsite drainage or detention facilities on the basis of the engineering feasibility of

a combined facility. No use of land or occupancy of buildings within the properties served by these facilities shall be permitted until completion of the retention and drainage structures, except upon specific approval.

d. The Public Works Department shall be authorized to approve of alternative methods of stormwater detention based on appropriate engineering studies that do demonstrate equal or better performance in accordance with the jurisdiction's stormwater management practices. Approved alternatives may include well maintained and landscaped lakes that may be provided to act jointly as detention reservoirs and recreation facilities or aesthetic focal points within forest preserve areas, public or private parks, housing developments, shopping centers, and industrial parks. Other control methods to regulate the rate of stormwater discharge which may be acceptable include, but not limited to, detention on flat roofs, parking lots, streets, lawns, underground storage, and oversized storm drains with restricted outlets.

e. Detention facilities and drainage structures shall, where possible, use natural topography and natural vegetation. In lieu thereof these shall have planted trees and vegetation such as

shrubs and permanent ground cover on their borders. All on-site facilities shall be properly maintained by the owner in such a way that they do not become nuisances. Nuisance conditions shall include: improper storage resulting in uncontrolled runoff and overflow; stagnate water with concomitant algae growth, insect breeding, and odors; discarded debris, and safety hazards created by the facility's operation.

f. Principal outlets such as weirs shall be constructed of concrete block or reinforced concrete with watertight joints. Outlet pipes shall be at least six (6) inches in diameter. Riser pipes, if used, shall be at least eight (8) inches in diameter.

g. No portion of any detention facility shall be located in any required buffer, street right-of- way, or within a flood hazard.

h. The 100-year ponding limits of a detention facility shall not encroach upon a public street.

i. Stormwater Detention Facilities.

(1) Stormwater detention facilities shall be constructed on a separate lot from all buildings in the development, and shall be dedicated to the City or County as a public improvement for maintenance in areas zoned AR, SR, HTR, LTR, and DR.

(2) A dedicated access corridor of at least 25 feet in width shall be required to provide access to the detention facility from a public street.

(3) Facilities shall be located on tracts of land designated on the recorded plat, with sufficient area around the perimeter to provide access for maintenance purposes and shall have an all-weather access road constructed from the public street to the detention facility. Said allweather access road shall at a minimum be constructed of gravel

and shall be approved by the Director of Public Works or their representative.

(4) Facilities that do not exclusively serve residential developments located within areas zoned AR, SR, HTR, LTR, and DR, are the perpetual responsibility of the land owner.

j. Detention facilities shall be enclosed with a minimum 4-foot high permanent fence around all facilities having a maximum water or undercut depth of more than four (4) feet or a bank slope greater than

1.5 to 1 and shall be equipped with a gate of sufficient width to permit entrance of equipment necessary to allow periodic maintenance activities. Fencing may be waived by the Director of Public Works in areas zoned other than residential and where the pond is more than 500 feet from a residential district or single or multi-family residence.

k. Construction of the stormwater management facilities shall be initiated as part of the grading of the site. Stormwater detention facilities shall be constructed prior to the installation of any other site improvements, and may be utilized under proper design as sedimentation

basins during development. Installation of all other storm drainage pipes, culverts, headwalls, and

ditches shall be coordinated with the construction of streets and/or other site improvements, as appropriate.

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:rome/zoning/6.15.5@2026-01-26-b45ca231be

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Rome Zoning Ordinance, 6.15.5. Stormwater detention facilities | Georgia Commons