6.3.2. Procedures for final plat approval.

About this text

  • As published by Municode, current through 2026-01-26
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

a. Prior to submission of an application for final subdivision plat approval, either:

(1) For minor subdivisions, the Public Works Director shall have certified that all lots are adequately served by existing streets and public utilities; or,

(2) All public improvements shall have been properly installed and completed in accordance with all requirements and standards of this Development Code.

(3) A guarantee in lieu of completed improvements shall have been received by the Public Works Department and approved by the Governing Body as provided under Article

6.4.6 of this Development Code.

b. Prior to submission, the applicant shall provide to the Public Works Department:

(1) As-built surveys for all public improvements as required by this Article if the installation of said improvements varies from the approved development plan.

(2) Payment for materials and installation of traffic signs and street name signs. Payment of the cost of street

striping or signalization, if required and not completed by the owner, shall also be included in the application.

(3) A maintenance bond providing adequate surety for the maintenance of all public improvements required by this Development Code in the subdivision for a period of 12 months following the date of final acceptance of said improvements.

c. Application for a final subdivision plat approval shall be made to the Public Works Department. The application shall include:

(1) A properly completed application form, as furnished by the Public Works Department, requesting final subdivision plat review.

(2) The original, two reproducible copies and nine prints of the final subdivision plat drawing prepared in conformance with the specifications

in this Section.

(3) Payment of all applicable final subdivision plat application and review fees, as established by the Governing Body from time to time.

(4) Evidence of payment for traffic and street name signs, and maintenance bond, to the Public Works Department.

d. The Public Works Department shall review the application for completeness within business five days of submission.

Incomplete applications will be returned to the applicant.

e. Within two weeks following receipt of the application, the Public Works Department shall indicate on the drawing or in writing all comments related to compliAPPENDIX B—UNIFIED LAND DEVELOPMENT CODE Art. 6, § 6.3.2 ance with this Development Code. The

Director of Public Works shall have sole authority to determine the applicability of any provisions of this Development Code to the final plat.

f. The owner shall be responsible for compliance with all codes, regulations and zoning requirements, and for the satisfaction of

all the noted and written comments of the Public Works Department. Resubmission of all revised drawings shall be made to the Public Works Department.

g. When all of the requirements of this Development Code, and any conditions of zoning approval, have been met, the Director of Public Works shall certify approval with signature and date on the plat.

h. Once the final subdivision plat has been so certified, it shall be forwarded to the Director of Planning for Approval, after which the Director of Planning shall sign and date the CERTIFICATE OF FINAL PLAT APPROVAL stamped or printed on a reproducible copy of the final Subdivision plat. The plat shall then be recorded by the Planning Department, or by the

applicant with the Planning Director's approval, with the Clerk of the Superior Court. An executed original of the approved drawing shall be transmitted to the applicant.

i. The final subdivision plat shall be submitted in digital form in a file format compatible with the Planning Department's GIS mapping system.

History

The history line the source prints at the end of the section.

(Ord. No. 2022-4-2, § I, 4-25-22)

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:rome/zoning/6.3.2@2026-01-26-007a837f8e

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Rome Zoning Ordinance, 6.3.2. Procedures for final plat approval | Georgia Commons