Sec. 22-36. Water supply and fire flow adequacy study required for permit issuance.
About this text
- As published by Municode, current through 2026-03-17
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
A water supply and fire flow adequacy study indicating sufficient water flow and pressure to serve both fire protection and domestic needs is required before the city will issue any of the following approvals:
(1) A development, land disturbance, or building permit for any multi-unit and single-unit attached projects.
(2) Any approval for a project that includes new or extended public water mains.
(3) Any approval for a project that the city engineer or fire marshal determines may significantly affect the water system.
For these projects referenced above in (1), (2), and (3), the city shall not issue a developFIRE PREVENTION AND PROTECTION § 22-36 ment permit, land disturbance permit, building permit, subdivision approval, site plan approval, or certificate of occupancy, until a water supply and fire flow adequacy study has been completed, submitted, and approved by the city. Rezoning and conditional use approvals shall not require a full water supply and fire flow adequacy study; however, the applicant shall provide conceptual water/ fire capacity information as requested by staff. A full study shall be required prior to issuance of a land disturbance permit or building permit for projects meeting
thresholds referenced in (1), (2), and (3), above. The water study and fire flow adequacy study shall not be required for any project that can show water supply is fed directly by a 48-inch water main. The city may, at its discretion, require a review of the study to be completed by a firm designated by staff;
in such instances, the applicant shall contract the services of the designated firm directly and shall be solely responsible for all fees and other costs associated with this process.
All testing, analysis, modeling, and reporting required as part of the water supply and fire flow adequacy study must comply with the city's adopted water supply and fire flow adequacy study technical manual, as it may be amended from time to time.
History
(Ord. No. 2026-03-003, § I, 3-3-2026)
Meetings that refer to this section
- Sandy Springs City Council, March 3, 2026 (Minutes)Names an ordinance in this section's history in the minutes: “Ordinance No. 2026-03-003”
Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.