3.21.11. Time Limits for Variances

About this text

  • As published by enCodePlus, retrieved 2026-11-14
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

a. Variances Approved by the Zoning Board of Appeals Approval of a variance pursuant to the provisions of this Ordinance shall become null and void unless the following is completed in the time period specified:

i. A variance shall expire after twenty-four (24) months from the date of approval if no development activity in furtherance of the variance has occurred. If a building permit, which relies on the variance, is issued and expires under the terms of this Ordinance, the variance requiring the building permit shall also become null and void at the same time the building permit expires.

b. Variances Approved by the Planning Commission A variance shall expire twenty-four (24) months from the date of approval if no development activity in furtherance of the variance has occurred. If a building permit, which relies on the variance, is issued and expires under the terms of this Ordinance, the variance requiring the building permit shall also become null and void at the same time the building permit expires.

c. Variances Approved bv the Savannah Downtown Historic District Board of Review A variance shall expire twenty-four (24) months from the date of approval if no development activity in furtherance of the variance has occurred. If a building permit, which relies on the variance, is issued and expires under the terms of this Ordinance, the variance requiring the building permit shall also become null and void at the same time the building permit expires. Approval of a variance pursuant to the provisions of this Ordinance shall be valid for the same time period as provided in Sec. 3.19. Upon the expiration of an approved Certificate of Appropriateness or the subsequent approved development plan or building permit that are consistent with the approved Certificate of Appropriateness, the variance shall become null and void.

*Commentary: Development activity can refer to applied for or issued demolition permits, applied for or issued building permits, and other site work permits that may be required for a project.*

History

The history line the source prints at the end of the section.

(Ord. of 05-14-2020(39), § 1, Ord. of 3-12-2026(11), § 1)

Read this code where it is posted (enCodePlus) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:savannah/zoning/3.21.11@2026-11-14-79548e8823

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Savannah Zoning Ordinance, 3.21.11. Time Limits for Variances | Georgia Commons