Sec. 4. Inspections.
About this text
- As published by Municode, retrieved 2026-11-11
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
(a) An authorized representative of the city shall [have] access to the work for inspection at any time. When an inspection for approval ofthe work is needed, the developer or his representative shall notify the community development department for inspections the following day.
(b) All phases of construction shall require a permit. These permits may be obtained from the city building inspector at the community development department after the construction plans are approved as each phase of work begins. A
copy of the permit, signed by the city building inspector, must be on file before any letter of approval can be written and before any additional permits can be issued for construction.
(1) Grading permit. Required after clearing and grubbing is completed, after debris is removed and prior to the beginning of any earth moving.
(2) Storm drainage permit. Required ifgrading work does not include installation of storm drainage pipe and other drainage
construction.
(3) Water and sewerline construction permit.
Required after grading permit has been finalized and prior to the laying of any water or sewer lines. Separate permits will be required ifwork is constructed by separate contractors.
(4) Curbing permit. Required after sewer permit has been finalized and prior to the installation of any curb and gutter.
(5) Base and paving permit. Required after curb and gutter permit has been finalized and prior to setting and priming base.
(c) A final field inspection of all improvements shall be held before conditional acceptance of the work and before the start of the one-year
maintenance period. As-built drawings must be submitted to the community development department prior to the start of the one-year maintenance period.
(1) When all construction falling under the community development department has been completed, the developer or his[/ her] representative shall meet with a representative from the community development department on the job site.
(2) All permits will be examined at this time to ensure that the work has been accepted and the construction plans checked against what has been constructed to ensure the work is completed.
(3) If all work has been completed and is approved, a letter of acceptance will be issued by the community development department.
(4) Stop work order. Any work not meeting the requirements of the standard design specifications shall be corrected by the contractor. Should the work not be corrected after notification by the city inspector, a stop work order shall be issued by the inspection department.
Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.