(a) Any building permit issued shall become invalid unless the work authorized by it shall have been commenced within six months of the date of issue or if the work authorized by the permit is suspended or abandoned for a period of six years.

(b) Any permit issued after the adoption of the ordinance from which this chapter is derived shall be valid for a maximum of 12 months, from the date of issue. Upon the expiration of this permit, if work has not passed a final inspection and received a certificate of occupancy, a stop work order shall be issued and a new permit, at the current fee schedule then in effect, shall be required to be purchased. Any permit issued prior to the ordinance from which this chapter is derived being adopted shall be valid for no more than 18 months from the date of issue. Any of the previously issued permits which are currently past the 18-month maximum validity period or shall expire in the upcoming months, shall be notified of this expiration in the following manner:

(1) The permit holder shall be given a notice of expiration. Said notice shall inform permit holder of the controlling regulation and the fact that their permit has expired. This notice shall give the permit holder an additional 30 days, from the date of the notice being issued, to complete the work authorized in said original and now expired, permit.

If at the expiration of this 30-day period the work has not been completed and the project given and passed a final inspection, the holder shall be informed that the previous permit has expired, all work must cease, and a new permit purchased at the rates in effect at the current time, and as though no other permits have been purchased (i.e., if it is a new home project, the building permit, plumbing, electrical, mechanical and grading permit must all be purchased again). The city inspector shall inspect the construction project and provide a list of items to be completed by the holder of the expired permit. The second, or reissue permit, shall be valid for a period no longer than six months. If it too expires, than a third permit, valid no longer than 30 days, shall be issued. All permits shall be purchased at the then current fee schedule. If the third permit expires, the city shall seek a court injunction and take action under the Standard Unsafe Building Abatement Code.

(2) If the original permit was issued without cost, the second and third permits acquired due to a lack of completing the project in a workmanlike manner shall be reissued only after a reissue fee of $50.00 is assessed for the subsequent permits.

(c) Stop work orders. The planning coordinator, city building inspector, chief of police, city manager or his designee, is duly authorized to issue stop work orders for cause, such as failure to obtain a building permit, unsafe work conditions or violations of Soil and Erosion Control Law, etc. Said stop work order shall be issued to the property owner and general contractor and require that the job site be conspicuously posted by the planning coordinator, or a city official so designated by the city manager. Any and all employees who defy this posted stop work order shall be arrested and cited and be subject to punishment in accordance with section 1-7.

Destruction and/or removal of the posted stop work order shall result in the property owner and/or the general contractor's agent responsible for the work, being cited in accordance with section 1-7.

(d) Failure to obtain a building permit prior to work begun. If a project is begun without having received a building permit prior to the work beginning, an additional fee, the higher of either double the regular fee to be charged or $50.00, shall be assessed; regardless of whether the work needing the permit would otherwise be assessed a fee or not. This fee shall not be assessed until the city effectively advertises the requirement to obtain a building permit, either through notices in the water bills or articles in the Tallapoosa Journal. A minimum of six individual publication efforts, at least one month apart from each other, must be accomplished prior to this failure to obtain a building permit in a timely manner fee being assessed. This fee is in effect as of the date of adoption of the ordinance from which this chapter is derived and completion of the advertising requirements, and may be changed from time to time by the mayor and council by resolution.

History

The history line the source prints at the end of the section.

(Ord. No. 01252, § 106-96, 12-12-2005)

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:tallapoosa/zoning/106-209@2026-11-11-512dd83d1b

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Tallapoosa Zoning Ordinance, Sec. 106-209. Construction progress | Georgia Commons