(1) Best Management Practices for industrial uses.

(a) Purpose and intent. It is recognized that construction and operations of industrial projects in close proximity to residences or other sensitive receptors may negatively affect the quality of life of those existing communities.

This section provides a framework through which industrial projects can be designed and operated in a way that lessens their impact on surrounding communities and the environment. It is meant to apply best management practices to help minimize potential impacts to sensitive receptors and is intended to be used in conjunction with the county land use ordinance and the Department of Natural Resources, Environmental Protection Department regulations.

This section does not replace the need for preparation of the appropriate projectspecific environmental review and application of any necessary measures that may arise out of that review. This section

provides a series of development and operational criteria that can be implemented to supplement project-level mitigation measures, in order to further reduce impacts related to industrial uses.

The application of this section is intended to be included in the conditions of approval as part of individual development projects.

This will provide a mechanism by which applicants and the public are made aware of how these guidelines are specifically implemented on a project-by-project basis and will provide an opportunity for county staff to monitor the individual conditions of approval. The following ordinances are organized into specific categories, to address potential quality of life issues from the initial application for a special use permit (if required) through the design process, to construction and through operations.

(b) Applicability.

(i) This section is intended to provide general guidance that will be appropriate for most industrial projects. Review under DNR/EPD will apply to any projects, regard- less of their square footage and size, and which may include technical reports including, but not limited, to noise, air quality, and traffic related impact evaluations. The community development office will use this section to review industrial

projects and document findings to be considered by the board of zoning appeals and planning commission and to the board of commissioners where the project does not conform to the county's ordinance.

(ii) The provisions of this section shall apply to all applications filed on or after the effective date of this section and to any application pending or under review as of the effective

date for which no final approval has been granted and no vested rights have accrued under applicable law.

(iii) This section is intended to apply to new industrial development and expansions requiring county review, permits, or approvals and shall not apply to the continued operation of lawfully existing uses except as otherwise required by applicable law.

(iv) This section is intended to supplement, and not replace, any usespecific standards otherwise applicable under section 7.7. Compliance with this section shall not relieve an applicant from compliance with any additional requirements applicable to a particular use under this article.

(c) Requirements applicable to all industrial uses.

(i) Pre-application meeting. Prior to submitting an application for a special use permit, or, where no special use permit is required, prior to submitting civil or construction plans for review, the applicant or his agent shall meet with the community development director, county planner, county engineer, county fire

marshal, and county environmental health officer (Troup County Health Department representative) to identify potential compliance issues and applicable requirements. This step does not require any formal application.

(ii) Application documentation.

1. The applicant or his agent should provide a map of the surrounding area, topographic data taken from USGS Quadrangle maps or other sources, the property boundary, and a sketch of the proposed layout. The sketch

should also include any existing conditions on the property that require special attention

of the applicant or his agent.

These may include but are not limited to a private cemetery, general area of any wetlands, whether the property is located in groundwater recharge area or any other environmentally sensitive area, or any other conditions as can be deemed from existing records.

2. Contact. Prior to issuance of any building permit for the requested use, the applicant or developer shall provide the county with current contact information (name, telephone number, address, and email address).

(d) Additional requirements for high intensity use. The following shall apply to high intensive use developments:

(i) Studies or analysis. Applicant or developer shall prepare:

1. An air quality study in accordance with the Department of Natural Resource, Environmental Protection

Division's Air Quality Control guidelines, Chapter 391-3-1 which includes both project specific and cumulative impact analysis;

2. A health risk assessment (HRA) if the facility's property line is within 1,000 feet of a sensitive receptor and the community development director determines, based upon competent evidence in the record, that the proposed use may create significant public health impacts not otherwise addressed through applicable federal, state, or local regulations. The basis for such determination shall be

documented in writing and made part of the project record;

3. A noise impact analysis performed by suitably qualified independent acoustic consultant to evaluate potential

impacts to the neighboring properties during construction and operations. The studies/ analysis shall be submitted with the special use application; if a special use is not required, said studies/analysis

shall be submitted with the request for a review of civil/ construction plans or a building permit application;

4. Such other technical studies, analyses, or reports prepared by a qualified professional as the community development director reasonably determines are necessary to evaluate significant site-specific impacts associated with the proposed use, including, but not limited to, hydrogeologic studies, groundwater impact analyses, well impact assessments, traffic studies, environmental assessments, or utility impact

analyses. The basis for requiring any such study shall be documented in writing and

made part of the project record.

To the extent a study, analysis, report, or assessment required by another provision of this section 7.7 substantially addresses the same subject matter and satisfies the purpose of a requirement under this subsection, the community development director may determine that such submission satisfies the corresponding requirement of this subsection and may waive the

need for duplicative submissions.

All studies, analyses, and reports required by this subsection shall be reviewed by the community development director, in consultation with the county engineer, county fire

marshal, environmental health officer, and other technical consultants or agencies as appropriate.

(ii) Notice to the public. In the case where the requested use is permitted by right, at least 14 days prior to the submittal of civil or construction plans for review, a sign shall be erected to be clearly visible from the

road nearest to the proposed site.

The sign shall be at least four feet by eight feet in size and shall be readable from the road by a person with 20/20 vision. The applicant shall certify compliance with this notice requirement at the time of plan submission.

(iii) Community liaison. Prior to issuance of any building permit for the requested use, the applicant or

developer shall designate a community liaison and provide the county with current contact information (name, telephone number, and email address). The community

liaison shall be responsible for receiving and responding to non-emergency complaints or inquiries related to

the use.

(iv) Construction and operational notifications. A construction traffic control plan (CTCP) shall be prepared and submitted with the civil/construction plans. The CTCP shall include proposed haul routes, anticipated road closures, and expected truck traffic volumes. The community development director, in consultation with the county engineer and other affected departments as appropriate, may require reasonable modifications to address

identified public safety, traffic, or infrastructure concerns.

(v) Emergency response. The facility will provide advanced notice and coordinate with the local first responders regarding backup generator testing to minimize disruption.

(vi) Community impact mitigation agreement. As a condition of approval of a special use permit for a highintensity use, the board of commissioners may require the applicant to enter into a community impact

mitigation agreement addressing identified off-site impacts reasonably anticipated to result from the proposed use. In evaluating the need

for a community impact mitigation agreement, the board of commissioners may consider objective factors, including, but not limited to, whether

a high intensity use:

1. Exceeds 5,000 square feet;

2. Is adjacent to a sensitive receptor; or

3. Involves substantial capital investment, utility demand, traffic generation, or other characteristics reasonably indicating the potential for significant off-site impacts.

The existence of one or more of the foregoing factors shall not, by itself, justify the requirement of a community impact

mitigation agreement, and, prior to requiring a community impact mitigation agreement, the board of commissioners shall make findings supported by the record

identifying:

1. The specific off-site impacts reasonably anticipated to result from the proposed use;

2. The evidence supporting the existence of such impacts;

3. The basis for determining that the proposed mitigation measures address such impacts;

and

4. The basis for determining that the proposed mitigation measures are reasonably related and roughly proportional to the anticipated impacts.

Any mitigation measures required pursuant to this subsection shall:

1. Be reasonably related to identified impacts of the proposed use;

2. Be roughly proportional in nature and extent to such impacts;

3. Be supported by findings contained in the record; and

4. Address impacts that cannot reasonably be addressed through otherwise applicable development standards, permit conditions, or other applicable regulations.

Any required mitigation measures shall be incorporated into the special use permit conditions and/or the community impact mitigation agreement approved by the board of commissioners.

(e) Compliance and enforcement. Compliance with the requirements of this section and any applicable permit conditions shall be required. Failure to comply may

result in the issuance of a stop-work order or other enforcement action authorized by the Troup County Code and applicable law until such noncompliance has been corrected. Nothing herein shall limit the county's authority to pursue

any other remedies or penalties authorized by the Troup County Code or applicable law.

(2) Junkyards, Junk Business, Salvage Operation, and/Motor Vehicle Towing.

(a) To prevent the creation of public nuisances and ensure the safety, health and welfare

of the citizens of Troup County, all junkyards, junk businesses and salvage operation/salvage yards in unincorporated Troup County shall be no less than 10

acres in area and shall be screened and buffered from view in accordance with [appendix C, section] 9.8.

(b) Motor Vehicle Towing.

(i) Areas where any towed vehicles are stored must be located a minimum of 300 feet from the nearest property with any zoning designation that allows residential dwellings.

(ii) Outdoor work/storage area where any towed vehicles are stored shall be in the rear yard only, surrounded by an eight-foot (8) solid visual barrier fence or wall. The visual barrier shall be painted or constructed of one (1) color and material providing a consistent appearance. The fence or wall shall provide screening of the outdoor work/storage area from the view of a public

thoroughfare and all surrounding properties. The fence or wall shall be maintained perpetually and immediately repaired as needed.

There shall be sufficient distance between stored vehicles and the fence or wall to allow for proper maintenance.

(iii) Vehicles shall not be stacked. Only one (1) vehicle height shall be permitted within the vehicle storage areas.

(iv) Motor vehicle towing services shall not allow objectionable smoke, noise, odors, or other adverse impacts on adjoining properties or the County.

No burning of any waste materials is permitted unless it is part of an approved contained heat system specifically for the reuse of waste materials.

(v) Any draining of fluids or removal of batteries from wrecked or towed vehicles must be completed in an enclosed structure on a concrete pad or floor or other impervious surface approved by the Community Development Director, or designee.

Any drained fluids shall be disposed of in a manner consistent with the Georgia Rules of Hazardous Waste Management and applicable Federal Regulations.

(vi) The site plan submitted with application for building permit or land disturbance showing the location of

structures, storage area, fencing and/or wall materials and parking plan for employees, customers and compliance with American with Disabilities Act, shall be reviewed by the Troup County Health Department, Troup County Engineer, Community Development Director and Troup County Community Development Director, or designee for compliance with these standards.

(vii) The construction or operation of the motor vehicle towing service shall not add to the contamination of the soil, create additional drainage runoff, or alter topography in such a way that creates hazards to the site, adjoining properties, or the County.

(viii) The ground surface in the outdoor work/storage area shall be covered with gravel, asphalt, or concrete or other material as approved by the Community Development Director, engineer, or designee.

(ix) Vehicles may not be stored at an outdoor work/storage area for longer than 12 months. Code enforcement officer, Community Development Director, or designee may inspect records at any time the business is open for compliance with this requirement.

(x) No wrecked or towed vehicles may be towed to the tow truck operator's residence for any reason.

(xi) Towing and wrecker service businesses are a separate type of business from salvage yards and junk yards. Towing and wrecker service

businesses that store and resell used vehicle parts or dismantle, demolish, and abandon inoperable vehicles shall comply with all Troup County

Ordinances that are applicable to salvage and junk yards.

(3) Marinas. When located within SU-R and LR zoning districts, such uses shall only be permitted when located on United States Army Corps of Engineers property.

(4) Data centers, crypto currency facilities, and data mining facilities. No person shall be permitted to site, place, build, construct or prepare any site for the placement of a data center

campus, crypto currency facility, or data mining facility as of the effective date of this article without having first obtained a special use permit for a data center campus, crypto currency facility, or data mining facility.

No application for approval of a data center campus, crypto currency facility, or data mining facility shall be deemed complete, accepted for processing, or scheduled for public hearing unless and until the applicant has submitted all

documentation required by this section that is applicable to the proposed design, phasing plan, and utility service plan, including all provider and other service-related confirmations, verifications and assurances required by this section.

The community development director is authorized to determine applicability and completeness of

applications and required supporting documentation for purposes of acceptance, scheduling, and processing.

(a) Acreage, facilities and public utility requirements.

(i) All facilities shall be located on parcels/lots sufficient to meet all requirements of this section, including all required setbacks.

(ii) Development of technological facilities greater than 500,000 gross square feet or covering more than

200 acres meets the Development of Regional Impact threshold (DCA's DRI Rules - Chapter 110-12-3-.01).

The applicant shall submit necessary documentation to the community development director and the Three Rivers Regional Commission for review and determination (Section B.12.5).

(iii) All facilities shall be connected to public water. Troup County, Georgia does not provide public water service.

Any extension, installation, or expansion of water mains, water lines, or other water system infrastructure

to serve the facility shall be provided by and subject to the standards and requirements of the applicable public water provider. Any water system extension, installation, or expansion located within the unincorporated area of Troup County,

or otherwise requiring county review or approval, shall comply with Appendix C, article C.8, section C.8.1 (Water System Expansion). The applicant shall obtain all reviews, recommendations, permits, and approvals required by section C.8.1, including review by the water review board and any approval required by the board of commissioners or the county manager (or designee), as applicable, prior to commencing construction of any water system improvements and prior to issuance of any land disturbance permit or building permit for the facility. Written documentation from the applicable public water provider

must confirm and verify (i) willingness to serve the facility at full build-out, and (ii) identification of

any required off-site improvements, extensions, or upgrades necessary to provide such service, all of which shall be completed or otherwise assured in a manner acceptable to the provider and the county.

(b) Sanitary sewer service. All facilities shall be connected to a central sewerage system;

such system shall comply with section D.1.2. Written documentation from the applicable sewerage provider must confirm and verify: (1) willingness to serve the facility at full build-out, and (2) identification of any required off-site improvements, extensions, or upgrades necessary to provide such service, all of which shall

be completed or otherwise assured in a manner acceptable to the provider and the county.

(c) Power and utility capacity. Prior to issuance of a building permit, the applicant shall provide written verification from

the applicable service provider demonstrating the following:

(i) System capacity. Adequate capacity is available within the applicable transmission, distribution, and substation infrastructure to serve the proposed use, and such capacity will not adversely affect the provider's ability to meet the existing and reasonably projected loaddemands of the surrounding service area.

(ii) Infrastructure adequacy. All utility supply equipment and related electrical infrastructure serving the proposed use are properly designed,

rated, and sized to safely accommodate the anticipated electrical demand.

(iii) Operational and cooling systems. Any systems utilized for cooling and operation of the facility, including, but not limited to, electrical, waterbased, or alternative systems, are sufficient for the proposed use and

will not create adverse impacts to public utilities or the surrounding region. An open-loop cooling system is prohibited. All water-based cooling systems serving information technology equipment in a data

center shall utilize either:

(1) A closed loop, non-evaporative cooling system; or

(2) A direct-to-chip cooling system operating within a sealed, recirculating loop.

(iv) Power quality. Operation of the facility will not result in electrical interference, harmonic distortion,

voltage fluctuations, or other power quality disturbances on or off the premises.

(v) Electrical inspection. Prior to issuance of a certificate of completion or certificate of occupancy, the applicant

shall provide written verification that all electrical work has successfully passed a final inspection performed by a qualified thirdparty electrical inspector.

(d) Building placement and orientation.

(i) All principal and accessory structures associated with campus operations shall be arranged, designed, and constructed to be harmonious and compatible with the site and with the surrounding properties and shall be placed at least 1,500 linear feet from property lines

of sensitive receptor sites.

(ii) Buildings shall be sited and oriented to minimize visual impacts of the bulk of the building when examined on a line-of-sight basis from adjacent public streets and sensitive receptors; minimize impacts on natural resources; and incorporate appropriate stormwater management practices within Troup County.

(iii) Campuses containing more than one building are encouraged to provide a variety in building size, massing, siting, and appearance by transitioning from smaller or lower buildings along street frontages to larger and

taller structures on the interior of the site. Consideration of topography shall be given to avoid placement of larger, taller, or more massive buildings in a prominent location on the property or along a public street.

(e) Maximum height. The maximum building height for all structures regulated under this subsection shall be no more

than 40 feet.

(f) Setbacks.

(i) All retention/detention pond(s) and utility substation(s) must be set back at least 1,500 linear feet from property lines of sensitive receptors.

(ii) Parking lots for campuses shall be set back at least 1,500 feet from all property lines.

(iii) Parking requirements. A minimum of one parking space per employee on the largest shift is required, plus an additional three visitor spaces.

(iv) Ground mounted equipment is prohibited in any required setbacks.

(g) Off street loading. A minimum of one loading space is required. Loading spaces/ bays are only permitted to be located on one elevation of the principal building.

(h) Noise/Vibration. The community noise equivalent level (CNEL).

(i) Community noise equivalent level (CNEL) at the boundary of the property containing a sensitive receptor shall not exceed 60 dBA.

(ii) The CNEL at the boundary of any developed property not containing a sensitive receptor shall not exceed 70 dBA.

(iii) Sound that is produced for not more than a cumulative period of one minute in any hour may exceed the standards above by up to ten dBA.

(iv) Where noise generated by the facility exhibits low-frequency or tonal noise at the boundary of a property

containing a sensitive receptor, a penalty of five decibels shall be added to the measured or modeled CNEL value for purposes of determining compliance with subsections (1) and (2). A tone shall be deemed present when the sound

pressure level in any one-third octave band between 20 and 500 Hertz exceeds the average of the two adjacent bands by at least five decibels.

(v) Testing of backup generators is limited to weekdays during the hours of 9:00 a.m. and 5:00 p.m.

(vi) Use of backup generators that exceed the maximum sound levels is permitted during a power outage, backup generators are required to have an

EPA rating of "Tier 4."

(vii) Emergency alerts where public health or safety and public agencies are involved, the maximum sound levels listed above do not apply.

(viii) A noise reduction barrier or device may be required at the discretion of the community development director when it is inconclusive that noise level tests do not conform to acceptable noise levels.

(ix) The limitations of 1,500, herein, shall not apply to any sensitive receptor that is established adjacent to the facility after the date of issuance of a certificate of completion or occupancy for the applicant's operation.

(x) The facility operators must provide a noise assessment report. The assessment shall be performed by a suitably qualified independent acoustic consultant. This report must be submitted to the community development director on a quarterly basis (every 90 days).

(i) Negative impacts. Any use or activity producing air emissions, dust, smoke, glare, exhaust, heat, or humidity shall be conducted in a manner that does not create a nuisance or exceed applicable federal, state, or local performance standards at or beyond the property line.

Such impacts shall be measured using generally accepted industry standards and methods, as determined by the community development director.

(j) Safety.

(i) The equipment used in any operation shall be housed in a metered, electrically grounded, and preengineered metal-encased structure with a fire rating designed to resist

an internal electrical fire for at least 30 minutes. The containment space shall contain baffles that automatically close in the event of fire, independent of a possible electric system failure.

(ii) Any campus proposing battery storage or any other device or group of devices capable of storing energy in

order to supply electrical energy at a later time, whether the energy is stored for use on-site or off-site, shall demonstrate compliance with National Fire Protection Association (NFPA) Standard 855, Installation of Stationary Energy Storage Systems, or similar standards and

must include fire suppression systems designed specifically for battery storage.

(k) Lighting.

(i) Horizontal surfaces. For the lighting of predominantly horizontal surfaces, such as, but not limited to,

parking areas, roadways, vehicular and pedestrian passage areas, loading docks, building entrances, sidewalks, bicycle paths, and site

entrances, luminaires shall be aimed down, and shall meet Illuminating Engineering Society of North America (IESNA) full cut-off/fully shielded criteria.

(ii) Non-horizontal surfaces. For the lighting of predominantly nonhorizontal surfaces, such as, but not limited to, facades, landscaping, and

signs, luminaires shall be shielded and shall be installed and aimed to not project their output into the windows of neighboring residences, adjacent uses, past the object being illuminated, skyward, or onto a public roadway.

(iii) Adjacent residential uses. The illumination projected onto a residential use shall at no time exceed 0.1 footcandle, measured lineof-sight and from any point on the receiving residential property.

(iv) Adjacent non-residential uses. The illumination projected from any property onto a non-residential use shall at no time exceed 0.5 initial footcandle, measured line-of-sight from any point on the receiving property.

(v) Glare. Vegetation screens shall not be employed to serve as the primary means for controlling glare. Rather, glare control shall be achieved primarily using such means as cutoff luminaires, shields and baffles, and appropriate application of lumi- naire mounting height, wattage, aiming angle, and luminaire placement.

(vi) LED lights. LED light sources shall have a correlated color temperature that does not exceed 3000K.

(vii) Luminaires. Luminaires shall not be mounted more than 20 feet above the finished grade of the surface being illuminated. No pole-mounted lighting on the roof shall be permitted.

(viii) Lighting after hours. Lighting for parking areas and vehicular trafficways shall be automatically extinguished nightly within � hour

of the close of the facility. On/off control shall be by an astronomic programmable controller with battery or capacitor power-outage reset.

When after-hours site safety/security lighting is proposed, such lighting shall not exceed 25 percent of the number of fixtures required or permitted for illumination during regular business hours. Where there is reduced but continued onsite activity throughout the night that requires site-wide even illumination, the use of dimming circuitry to lower illumination levels by at least

50 percent after 11:00 p.m. or after regular business hours, or the use of motion sensor control, shall be permitted.

(l) Perimeter fencing/security. Fences shall be a minimum of eight feet, in height above ground and shall be of highquality design and materials.

(m) Power lines and campus electric utility substations.

(i) Electric utility substations must include year-round opaque landscaping or a screen wall with a minimum height of eight feet to minimize

visual impact.

(ii) Electric utility substations on the same property as the facility they serve must be located on the side or rear of a principal building so they are screened from public view and must not be located in a required front yard. On-site substations do not require a buffer or screening between the principal building and the substation.

(iii) Burying power lines serving the property is strongly encouraged. Onsite power lines of 34.5 kV and below must be buried.

(iv) The electric utility substation shall be subject to applicable zoning district setback requirements.

Setbacks shall be measured from the edge of the compound containing the substation to the property boundary of the lot it occupies.

(n) Emergency contact information. Each campus operation shall provide 24-hour emergency contact signage visible at the access entrance. Signs shall include the company name (if applicable), the owner/ representative's name, the telephone number, and the corresponding local power company's name and telephone number.

(o) Sensitive receptors

(i) Orientation. Unless physically infeasible, loading docks, truck entrances, and truck drive aisles shall be oriented away from abutting sensitive receptors.

(ii) Location and mitigation. To the maximum extent feasible, loading docks, truck entries, and truck drive aisles shall be located as far as practicable from nearby sensitive receptors. Screening as described in subsection (o) shall be provided. In determining feasibility, the county shall consider applicable federal, state, and local laws and regulations, including traffic safety and emergency access requirements, and

shall balance public safety needs with the potential operational impacts of the development on nearby sensitive receptors.

(p) Buffer and screening. All campus operations shall provide buffer and screening along all property boundary lines, except

for areas of ingress and egress into the site.

(i) Sites abutting sensitive receptors shall maintain 300 linear feet of vegetative buffer.

(ii) Sites abutting non-sensitive receptors shall maintain 75 foot vegetative buffer.

(iii) Use of existing vegetation for landscaping and screening is strongly encouraged and may be substituted with new plantings if approved by the community development director.

(iv) Service areas. Loading bays, refuse collection areas, and service entrances shall be screened from view from existing or planned public roads, sensitive receptors, and residential zoning districts. Screening may include year-round landscaping or a screen wall of an

appropriate height to mitigate visual impacts as determined by a line-ofsight study submitted by the applicant.

(v) Mechanical/electrical equipment screening.

(1) Ground-mounted equipment adjacent to and serving the principal building shall be completely screened behind an opaque wall or fence. When the equipment is located between buildings, a combination of walls and gates may be used at the openings between

buildings. When in or adjacent to an industrial use or zoning district, ground-mounted equipment screening is only required from any existing or planned

public road.

(2) All rooftop-mounted equipment shall be screened by a parapet wall, equipment penthouse, or visually solid screen on all four sides that is constructed of materials complementary to those used in the exterior construction of the principal building. This shall be accomplished by setting the equipment penthouse or screened area back from the façade of the building such that the top of the equipment penthouse or screen is below a 45-degree line drawn from the top of the parapet. Roof-top equipment to be screened includes, but is not limited to, the following: cooling, ventilation, and power supply machinery.

(3) The required number of plant units shall be calculated in accordance with article 9 of Appendix C of the Troup County Code.

(4) Buffer along roadways shall be measured from the street rightof-way line.

(5) Where a lot line drainage or utility easement is required, the buffer shall be measured from the inside edge of the easement.

(6) Buffers shall not include environmental encumbrances such as, but not limited to, wetlands, wetland transition areas, riparian buffers, and flood hazard areas as may be imposed by outside agencies.

(7) Buffers may be located within the required building setback lines. No impervious surface is permitted within the buffer aside from access drives, sidewalks, and associated improvements.

(q) Woodland disturbance. Woodland disturbance, including alteration or removal of any hedgerows, shall be minimized. No portions of tree masses, tree lines, hedgerows, or individual freestanding trees measuring six inches or greater in diameter at breast height (DBH) shall be removed unless it is clearly necessary to effectuate the proposed development. In no case shall more than 50 percent of any existing tree masses, tree lines, hedgerows, or individual freestanding trees with sixinch or greater DBH be removed. For purposes of this subsection, a woodland

is defined as a tree mass or plant community in which tree species are dominant or codominant and the branches of the

trees form a complete, or nearly complete, aerial canopy. Any area, grove, or stand of mature or largely mature trees (i.e., six-inch or greater DBH) covering an area of .25 of an acre or more, or consisting of more than 50 individual trees six inches or greater DBH, shall be considered

a woodland.

(r) Environmental and community impact analysis. Prior to the commencement of the special use hearing, the applicant shall provide environmental and community impact analysis. The environmental and community impact

analysis shall include:

(i) A narrative description of the nature of the on-site activities and operations, including the market area served by the facility, the hours of

operation of the facility, the total number of employees on each shift, the times, frequencies, and types of vehicle trips generated, the types of materials stored and the duration period of storage of materials.

(ii) A site plan of the property indicating the location of proposed improvements, flood plains, wetlands, waters of Troup County and cultural and

historic resources on the property and within 500 feet of the boundaries of the property.

(iii) Evidence that the disposal of materials will be accomplished in a manner that complies with state and federal

regulations.

(iv) An evaluation of the potential impacts of the proposed use, both positive and negative, upon emergency services and fire protection, water supply, sewage disposal, solid waste disposal, public facilities.

An environmental impact assessment shall be performed to assess any environmental impacts that are

likely to be generated (e.g., odor, noise, smoke, litter, dust, glare, heat islands, vibration, electrical disturbance, wastewater, stormwater, solid waste, etc.) and specific measures employed to mitigate or

eliminate any negative impacts. The applicant shall further furnish evidence that the impacts generated by the proposed use fall within acceptable levels, as regulated by

applicable laws and ordinances. The assessment shall be prepared by a professional engineer, ecologist, environmental planner, or other qualified individual.

(v) Threatened and endangered species.

The applicant shall provide a letter regarding threatened and endangered species dated within two years of the submission of an application for a special use permit or subdivision and land development,

whichever is first. The applicant shall comply with all measures to avoid, minimize, or mitigate impacts to endangered, threatened, and special concern species and their habitat.

(s) Building colors. External building materials shall be of colors that are lowreflective, subtle, or earth tone.

Fluorescent and metallic colors shall be prohibited as exterior wall colors.

(t) Emergency responders. The applicant shall coordinate with the Troup County emergency management coordinator to ensure there is adequate radio coverage for emergency responders within the building based upon the existing coverage levels of the Troup County Public Safety Radio Communications System at

the exterior of the building and shall install enhancement systems as needed to meet compliance.

(u) Civil plans. The applicant must submit a stormwater management plan to the Troup County Roads and Engineering Department prior to proceeding with the proposed development.

(v) Solar panels. All building roofs shall be designed and constructed in a manner that facilitates and optimizes the installation of a rooftop solar photovoltaic (PV) system. Any portion of a building's rooftop

that is not covered with solar panels or other utilities shall be constructed with light colored roofing material with a solar reflective index of not less than 78. This shall be the minimum solar reflective rating of the roof material for the life of the building. On buildings over 400,000 square feet, prior to the issuance of a certificate of occupancy, Troup County shall ensure rooftop solar panels are installed and operated in such a manner that they will supply as much power as needed to operate the facility as is feasible.

(w) Decommissioning and financial assurance.

(i) Decommissioning plan required. A decommissioning plan shall be provided by the applicant for all data centers, average/hyperscale;

crypto currency facilities, average/ hyperscale; and data mining facilities, average/hyperscale. The decommissioning plan shall identify

the measures that will be taken if the facility ceases principal operations, including securing the site, removal of computing and

operational equipment, removal and lawful disposal of fuel, oils, refrigerants, batteries, and other regulated or hazardous materials, and restoration of the site to a safe and stable condition.

(ii) Trigger. Decommissioning obligations shall be triggered when a facility described in subsection (i) ceases principal operations for a continuous period of 180 days, unless extended in writing by the community development director upon a documented showing of active

efforts to resume operations.

(iii) Average/hyperscale facility bond requirement. Prior to issuance of any building permit, data centers, average/hyperscale; crypto currency facilities, average/hyperscale; and data mining facilities, average/ hyperscale shall post financial assurance in the form of a surety bond in favor of the county in an amount

not less than 100 percent of the estimated cost of the decommissioning and site restoration, based on a third-party cost estimate prepared

by a qualified professional and approved by the community development director.

(iv) Small facility treatment. Data centers, small; crypto currency facilities, small; and data mining facilities, small shall not be required to post a decommissioning surety bond

as a matter of course. However, where warranted by site-specific circumstances, the county may require, as a condition of approval, a decommissioning plan and alterna- tive financial assurance in a form acceptable to the county, including cash escrow, irrevocable letter of credit or other comparable security approved by the county.

(v) Updates. Any required surety bond or other approved financial assurance shall remain in effect until the county verifies completion of decommissioning and restoration. The amount shall be reviewed and

updated not less frequently than every five years based on an updated third-party cost estimate approved by the community development director.

(vi) County right to use security. If the owner or operator fails to complete required decommissioning within the time required by this section, the county may draw upon the posted surety bond or other approved financial assurance to complete the required work and recover reasonable administrative and professional costs incurred by the county in doing so.

(vii) No expansion of lien rights. Nothing in this section shall be construed to create any lien right beyond those otherwise authorized by applicable law.

(viii) Enforcement. Failure to maintain required financial assurance or to timely complete decommissioning shall constitute a violation of the Troup County Code and shall be subject to enforcement under section 1-19 of chapter 1 of the Troup County Code and article II of

Appendix A of the Troup County Code.

(x) Violations and enforcement.

(i) Any violation of this section, any approved site plan, phasing plan, utility service plan, decommissioning obligation, or any condition of a special use permit or other approval

issued under this section shall constitute a violation of the Troup County Code and shall be enforced in accordance with section 1-19 of chapter 1 of the Troup County Code and article II of Appendix A of the Troup County Code.

(ii) Without limitation of any other lawful enforcement actions, the community development director may issue a stop-work order, withhold or

suspend building permits, and withhold any certificate of occupancy or completion for any phase not in

compliance with this section or applicable permit conditions.

(iii) Repeated or material noncompliance with permit conditions, after notice and opportunity to cure as

provided in article II of Appendix A of the Troup County Code, may constitute grounds for modification, suspension, or revocation of an approval or permit issued under this section.

(iv) Where a violation presents an immediate threat to public health or public safety, including violations involving emergency access, fire protection systems, hazardous materials handling, unlawful utility operation, or failure to maintain required decommissioning security,

the county may utilize the emergency notice and enforcement provisions of article II of Appendix A of the Troup County Code and other remedies available under applicable law.

(v) Civil and criminal penalties, if pursued, shall be those otherwise authorized under article II of Appendix A of the Troup County Code, Section 1-19, of the Troup County Code, and other applicable law.

History

The history line the source prints at the end of the section.

(Ord. No. 2025-03, 6-3-2025; Ord. No. 2026-06, § II, 5-5-2026; Ord. No. 2026-07, § I, 6-16-2026)

Meetings that refer to this section

Found 2: meetings of this government whose minutes or machine transcripts name this section, or an ordinance in its history line, newest first. Found by rule from those records' own words. A reference is a pointer to another record, not a statement that the section applies or was changed.

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:troup-county/zoning/7.7@2026-06-16-adad91e556

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Troup County Zoning Ordinance, Sec. 7.7. Industrial uses | Georgia Commons