Troup County · Zoning Ordinance
Appendix C - DEVELOPMENT AND PERMITTING / Article 10 - WATERSHED PROTECTION DISTRICT
Sec. 10.3. Underlying zoning, conditions, and performance standards.
About this text
- As published by Municode, current through 2026-06-16
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
(1) Regulations of the Underlying Zoning District. Unless otherwise noted in the watershed district regulations, the regulations of the underlying zoning district shall be maintained and not affected.
(2) Conditions and Performance Standards.
All uses in the watershed districts are subject to the following conditions and performance standards:
(a) A buffer shall be maintained for a distance of 100 feet on both sides of the stream as measured from the stream banks and for
a distance of 150 feet from the reservoir boundary of a water supply reservoir.
(b) No impervious surface shall be constructed within a 150-foot setback area on both
sides of the stream as measured from the stream banks or within a 150-foot setback area from a reservoir boundary.
(c) Septic tanks and the drainfields of septic tanks are prohibited within 150 feet of a stream bank or of a reservoir boundary.
(3) Exemptions from buffer and setback requirements:
(a) Mining activities permitted by the Department of Natural Resources under the Surface Mining Act from the provisions
of water supply watershed protection plans.
(b) Utilities from the stream corridor buffer and setback area provisions of water
supply watershed protection plans in accordance with the following conditions if the utilities to be located in the buffer or setback areas cannot feasibly be located outside these areas:
(i) The activity shall be consistent with best management practices
established by the Georgia Forestry Commission of the Georgia Department of Agriculture.
(ii) The activity shall not impair the quality of the drinking water stream.
(4) Site plans required. Except for the exemptions listed in subsection (6) below, all forms of development within the watershed districts shall be required to have a site plan prepared and approved according to this article before any building permits or other development related permits may be issued or any land disturbing activity may take place. Each site plan submitted under this article shall include the following:
(a) A site plan drawn to a scale and showing all planned improvements including the
width, depth, and length of all existing and proposed structures, roads,
watercourses, and drainage ways; water, wastewater, and stormwater facilities;
and utility installations.
(b) Location, dimensions, and area of all impervious surfaces, both existing and
proposed, on the site.
(c) The orientation and distance from the boundaries of the proposed site to the
nearest bank of an affected perennial stream or water body.
(d) Elevations of the site and adjacent lands within 200 feet of the site at contour
intervals of no greater than five (5) feet.
(e) Location and detailed design of any spill and leak collection systems designed for the purpose of containing accidentally
released hazardous or toxic materials.
Calculations of the amount of cut and fill proposed and cross sectional drawings
showing existing and proposed grades in areas of fill or excavation. Elevations, horizontal scale, and vertical scale must be shown on cross sectional drawings.
(5) Activities to comply with site plan. All development activities or site work conducted after approval of the site plan shall conform with the specifications of said site plan. Significant changes to the site plan, that would alter the amount and velocity of stormwater runoff from the site, increase the amount of provisions of impervious surface within the development, alter the overall density of development, result in a considerable increase in the amount of excavation, fill, or removal of vegetation during construction, or otherwise result in an alteration of the overall appearance of the development as proposed, can be amended only with the approval of the Troup County Community Development Director. Minor changes such as realignment of roads, streets, or minor alterations to drainage structures and other infrastructure, to meet unexpected conditions are exempted from this requirement.
(6) Exemptions from site plan requirement.
The following activities and developments are exempt from the requirement of detailed site plans:
(a) Single-family detached dwellings constructed within a subdivision of fewer than five (5) parcels.
(b) Repairs to a facility that is part of a previously approved and permitted
development.
(c) Construction of minor structures such as sheds, or additions to single-family dwellings.
(d) Agriculture and forestry. Normal agricultural activities including planting and harvesting of crops are exempted if
they conform to best management practices established by the Georgia Department of Agriculture. Silvicultural activities must conform to best management practices established by the Georgia Forestry Commission.
(e) Mining activities. All mining activities permitted by the Georgia Department of
Natural Resources under the Georgia Surface Mining Act are exempt.
(7) Use limitations. Within the watershed districts the following limitations on permissible uses shall apply in addition to the regulations of the underlying zoning district:
(a) New sanitary landfills are allowed only if they have synthetic liners and leachate
collection systems.
(b) New hazardous waste treatment or disposal facilities are prohibited.
(c) New facilities which handle hazardous materials of the types and amounts
determined by the Department of Natural Resources, shall perform their operations on impermeable surfaces having spill and leak collection systems as
prescribed by the Department of Natural Resources.
(8) The impervious surface area, including all public and private structures, utilities, or facilities, of the entire water supply watershed shall be based upon an assessment of the percentage of impervious surface present in the watershed district at the time of the adoption of this article.
New impervious surface will be allowed up to the point where 25 percent of the watershed district as a whole is comprised of impervious surface.
History
(Ord. No. 2025-03, 6-3-2025)
Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.