Sec. 8.1. Water system expansion.
About this text
- As published by Municode, current through 2026-06-16
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
(1) Applicability of article provisions. This article shall apply to the development of all water systems constructed in unincorporated areas within the boundaries of the County.
(2) Withholding of construction or building permit until compliance with article provisions effected. The County may withhold the issuance of any construction or building permit and/or occupancy or use permit in any subdivision, development or improvement to which this article applies, until there is compliance with the regulations and specifications contained in this article.
(3) Water review board.
(a) Established. The water review board is hereby established.
(b) Composition; terms. The water review board shall consist of five (5) members.
Initially, one (1) member shall be appointed for a term of one (1) year, a second member shall be appointed for a term of two (2) years, a third member shall be appointed for a term of three (3) years, a fourth member shall be appointed for a term of four (4) years, and a fifth member shall be appointed for a term of
five (5) years. The term of each member shall end on June 30 of his expiration year. The five (5) members shall elect one (1) of their number to serve as chairman of the water review board.
(c) Authority; responsibilities. The water review board shall have the following
authority and responsibilities:
(i) To review all applications for new and/or expansion of existing water lines and systems in the unincorporated areas of the County;
(ii) To provide to the Board of Commissioners recommendations for the approval of or denial of applications
pertaining to water systems in the unincorporated areas of the County;
(iii) To offer any recommendations regarding matters concerning water systems, regulations, and/or finances;
(iv) To work with the various cities located within the County in the improvement of water service in the unincorporated areas of the County;
(v) To have the authority to recommend that the Board of Commissioners make variances, when it is feasible or necessary, from this
article; and (vi) To work with the various County offices and state agencies to ensure an adequate and improved water system for the citizens of the County.
(d) Reception of construction plans and specifications. The water review board shall be the authorized officer of the County to receive construction plans and specifications as contemplated and
required by subsection (6) of this section.
(4) Statement of intent and purpose of article.
(a) It is the intent of the Board of Commissioners to provide the citizens of the unincorporated County areas with a sufficient water supply for the purpose of their health, safety, welfare and
convenience. It is also the intent of the Board of Commissioners that water expansion progress in an orderly fashion for the purpose of providing the most water
at the least cost. Consideration for service will be based on the need for water and
the feasibility of providing service.
(b) It is the purpose of this article to ensure that all public and private water systems, constructed in the unincorporated areas
of the County, satisfy all existing and future County, state and federal regulations. Both public and privately owned water systems in the unincorporated areas of the County shall be constructed only
after the plans have been approved as outlined in this article and a construction permit has been granted. Only systems approved and constructed in
accordance with this article will be allowed to operate in the County.
(5) General design standards. General design requirements for both government owned and privately-owned public water systems are set out herein. The County requires a minimum of 500 gpm at a residual pressure of 20 psi at all fire hydrants. Where named products and materials are offered in this article, substitute products and materials may be used, but only with the approval of the County manager or the manager's authorized designated representative.
(a) The developer shall be required to install an adequate water supply system to, and
with the area to be developed including service lines to each lot as shown, of the development.
(b) Water mains proposed along existing frontage roads or proposed main thoroughfares shall be sized consistent with the County water expansion map, designated as the master map dated 1987.
(c) All water mains shall be six (6) inches in size or larger, except for short (500 feet or less), dead-end or connecting road or
street in residential areas.
(d) Dead-end lines shall be minimized by looping of all mains when possible.
(e) Minimum horizontal distances between water and sewer lines shall be 10 feet.
The distances between water and sewer lines, when crossed, shall be 18 inches with the water line above the sewer line.
Minimum horizontal and vertical distances between water lines and other underground utilities or structures shall be two (2) feet.
(f) Design for all creek crossings shall be approved by an authorized representative of the County.
(g) All crossings of paved roads or streets shall be by the bore method, unless
otherwise approved prior to installation.
All pipe six (6) inches and larger in diameter shall require casing to be carried with the bore. A County road or street may be open cut, or bored without casing, only after written permission has been received from the designer. All pipe placed in open cut trenches or uncased
bores under paved roads or streets shall be ductile iron. All pipe shall have a
minimum cover of four (4) feet from finish grade of street or road.
(h) All crossings of driveways shall be by means of uncased bore or open cut as
may be determined by the County representative. Where open cut method is required, existing concrete and asphalt driveways shall be sawed and the debris
removed prior to trenching. When pipe installation is complete, the driveway shall be backfilled, tamped, and damaged areas replaced with material consistent with the driveway as soon as
possible.
(i) Tees, crosses, valves and other necessary fittings shall be provided at all major
intersections and at all points required by the water review board to provide for future expansion.
(j) Magnetic detection tape shall be placed directly over all nonmetal pipe at a
maximum depth of two (2) feet from finished grade.
(k) Fire hydrants shall be located at intervals not to exceed 1,000 linear feet along the road or street right-of-way. Generally,
fire hydrants serving commercial, industrial, or residential dwelling uses shall be located at intervals not to exceed 500 linear feet along the road or street right-of-way. Final approval of fire hydrant placement shall be approved by the Troup County Fire Marshall.
(l) All fire hydrants shall be located on the right-of-way and shall have a valve
installed between the main and the fire hydrant.
(m) All fire service lines and connections with private fire hydrants, hand hose
connections, sprinkler heads, and any supply other than domestic lines shall have installed an underwriter approved double detector check valve.
(n) Shutoff valves shall be installed along the main line at intervals not greater
than 2,000 feet.
(o) Shutoff valves shall be installed on all branch lines as well as on each side of the branch as close to the intersection as
possible.
(p) Flush valves are required on dead-end water mains that do not have a fire
hydrant at the end.
(q) Each underground valve shall include a valve box placed vertically to allow operation of the valve. Valve boxes not located in roadways shall have a precast concrete collar placed level around the top for
protection.
(r) Service lines shall be provided to all residential lot property lines. Lines shall be three (3)-fourths-inch minimum
diameter and furnished with meter box, curb and corporation stops.
(s) Water services for commercial, industrial, or multifamily residential shall be
adequate to provide for the specific needs of the installation, including adequate
fire protection.
(t) Location of service laterals shall be indicated precisely on drawings. Services shall extend from the water main to the
property line of each lot. Each line shall have a meter stop placed on its end and
stubbed into a meter box set by the developer.
(6) Submittal and approval standards.
(a) It is the purpose of the standards of this section to establish the minimum requirements for the information to be submitted to and approved by the Board of Commissioners or their designee.
(b) The developer shall submit to the authorized officer of the County two (2) sets of construction plans and specifications for approval. Approval of the plans and specifications may be given by the
appropriate authority. Work shall not begin until all approvals regarding materials, methods of construction, environmental impact, railroad permits,
department of transportation permits and other required approvals are received
from the respective approving agencies.
(c) The information shall be submitted to the Board of Commissioners or their
designee for approval at least 60 days prior to the start of construction. The information submitted with the plans shall include the following in addition to the construction plans and specifications:
(i) Number of customers to be served.
(ii) Location and depth of water mains.
(iii) Tap-on fees to be charged.
(7) Paying cost of main relocation for road work. The owner of any water system located on road rights-of-way of the County shall pay all cost of relocation of any water mains and appurtenances within the public rights-of-way which is necessary for roadway improvements.
(8) Construction standards. The standards to be used in the design, material, implementation, etc., of any water system located in the unincorporated area of the County shall meet or exceed the standards for design, material implementation, etc., then in effect for Troup County. All questions regarding such matters shall be submitted to the water review board whose determination shall be final.
History