Sec. 6-8. Stormwater drainage.

About this text

  • As published by Municode, current through 2010-11-02
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

The subdivider shall provide adequate stormwater drainage in accordance with these regulations and applicable county specifications. Where drainage conditions dictate, open ditches shall be paved. The subdivider shall also provide for adequate drainage of springs or other groundwater drainage.

The drainage system for a subdivision, commercial or industrial development shall be designed in accordance with sound engineering principles and procedures such that all salable parcels included in the final plat are positively drained.

The drainage system shall be designed to accommodate drainage from adjacent lands which naturally drain to or through the lands being subdivided. The drainage system shall be designed to not significantly affect the natural drainage onto adjacent lands unless appropriate easements are obtained by the developer from the owner of such adjacent lands concurring with the proposed drainage design. Evidence of such concurrence shall be submitted to the county engineer along with the improvement plans and specifications.

Drainage facilities that are designed to handle flowing water (e.g., culverts, weirs, etc.) shall be hydraulically designed to function when subjected to the maximum flow rate that can be expected to occur no more often than once in 25 years.

Drainage facilities that are designed to handle water accumulations (e.g., detention ponds with overflow provisions) shall be designed to accommodate the maximum water level that can be expected to occur no more often than once in 25 years. Necessary drainage facilities including, but not limited to, culverts, rights-of-way, and easements, may be dedicated to Turner County, at no expense to the county, and at the option of the county. Areas required for maintenance shall be cleared of all trees and underbrush which would interfere with maintenance of the facility.

All drainage systems discharging into any creek, stream, or natural body of water including, but not limited to, wetlands as determined by the U.S. Army Corps of Engineers shall pass through an approved sedimentation or detention pond prior to such discharge.

A master drainage plan shall be submitted to the county engineer simultaneous with preliminary plat submittal at which time technical design criteria will be established.

6.8.1. Soil erosion control. A soil erosion control plan, prepared in accordance with Turner County soil erosion and sedimentation control ordinance's latest revisions, shall be submitted to the county engineer simultaneous with [the] preliminary plat.

6-8.2. Wetlands. Wetlands shall be addressed per the Part V Environmental Planning Standards. Location of wetlands boundaries shall be delineated on the preliminary and final plats. All preliminary plats delineating wetlands shall have on the face of said preliminary plat the note: "No fill or work shall be permitted within jurisdictional wetlands without a prior permit from the U.S. Army Corps of Engineers."

6-8.2.1. All minimum lot areas per designated zoning classification requirements shall be calculated upland of any wetlands boundaries within or contiguous to the project.

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:turner-county/zoning/6-8@2010-11-02-7d7f84331f

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Turner County Zoning Ordinance, Sec. 6-8. Stormwater drainage | Georgia Commons