Sec. 16-370. Permit application procedure.

About this text

  • As published by Municode, retrieved 2026-11-11
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

(1) Applications for post-construction stormwater management permits shall be filed with the city on a permit application on a form provided by the city for that purpose.

(2) Permit applications shall include the items set forth in section 16-330 (two copies of the stormwater management design plan and the stormwater management inspection and maintenance agreement and plan, shall be included).

(3) The city shall inform the applicant whether the application, stormwater management design plan, and inspection and maintenance agreement and plan are approved or disapproved.

(4) If the permit application, stormwater management design plan, or inspection and maintenance agreement and plan are disapproved, the city shall notify the applicant of such fact in writing. The applicant may then revise any item not meeting the requirements of this division and resubmit the same, in which event subsection 16-370(3) and this section shall apply to such resubmittal.

(5) Upon a finding by the city that the permit application, stormwater management design plan, and inspection and maintenance agreement and plan, if applicable, meet the requirements of this division, the city may issue a post-construction stormwater management permit for the land development project, provided all other legal requirements for the issuance of such permit have been met.

(6) Notwithstanding the issuance of the permit, in conducting the land development project, the applicant or other responsible person shall be subject to the following requirements:

(a) The applicant shall comply with all applicable requirements of the approved stormwater management design plan and the provisions of this division and shall certify that all land clearing, construction, land development, and drainage will be done according to the approved stormwater management design plan;

(b) The land development project shall be conducted only within the area specified in the approved stormwater management design plan;

(c) The city shall be allowed to conduct periodic inspections of the project in accordance with subdivisions 5 and 6 of this division;

(d) No changes may be made to an approved stormwater management design plan without review and written approval by the city; and

(e) Upon completion of the project, the applicant or other responsible person shall submit a statement certifying that the project has been completed in accordance with the approved stormwater management design plan and as-built plans for the stormwater management system, as required by section 16-550.

History

The history line the source prints at the end of the section.

(Ord. No. 42-2014, § 1, 10-10-2014)

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:tybee-island/zoning/16-370@2026-11-11-1d548a83db

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.