See. 5-010. Permits required for construction.

About this text

  • As published by Municode, retrieved 2026-11-11
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

The following is a list of permits needed for construction of a building or structure or the movement of a building or structure that may be needed for any type of land development in the city.

(A) Building permit. All building permits seeking to expand the exterior of any existing structure or seeking to construct any new structure must be accompanied by a valid survey depicting, among other things, the present location of all property lines and structures then on the property.

(B) Relocation permit. A relocation permit is required any time a manufactured home, trailer, out building, house or structure is moved from any location to any lot or parcel within the city limits. Buildings used for the purpose of storage only with no need for electricity or plumbing are exempt from this requirement. Electrical, mechanical and plumbing permits are included within this permit.

(C) Sign permit. Prior to the erection of a sign for either on-premises or off-premises advertising, the zoning administrator must first issue a permit in accordance with the sign regulations set forth in article 6. Permits are required for both temporary signs as well as permanent signs.

(D) Demolition permit. Prior to destruction of a building, structure, or sign, a demolition permit is needed. Such permit may be attained from the city code enforcement department.

(E) Electrical permit. An electrical permit is needed before installing any electrical wiring or fixtures. This permit is not needed if a relocation permit or building permit has already been issued on the structure.

(F) Plumbing permit. A plumbing permit is needed whenever a plumber installs a new plumbing system in an existing structure. This permit is not needed if a relocation permit or building permit has already been issued on the structure.

(G) Mechanical permit. A mechanical permit is needed before a licensed installer may install any mechanical device such as a heating and/or cooling system for air or water.

This permit is not needed if a relocation permit or building permit has already been issued on the structure.

(H) Land clearing, disturbance or excavation permit. Regardless of the use of the land, a permit is required prior to the clearing of trees, topsoil, or water on any parcel of land in the city. A drainage plan with supporting calculations is required prior to the issuance of any permit for all new construction. The plan and calculations shall be prepared by a professional engineer licensed by the state to provide such services.

Furthermore, there shall be no excavation or addition of soil, trees, or water until all proper permits are obtained. This permit is not needed if a relocation permit or building permit has already been issued on the structure.

(1) Tree removal. A tree removal permit is required if a person intends to remove either a significant tree or any number of trees that will result in a tree density of less than required. This permit is required regardless of any other permits obtained.

(J) Reserved.

(K) Prohibit placing materials in the marshlands. Notwithstanding any other provision of any ordinance or regulation to the contrary, no permit for building, land clearing, land filling or for the addition of materials to any area of "marsh," "marshlands," "coastal marshlands," "vegetated marshlands," or isolated freshwater wetlands as such terms are now or hereafter defined by the Coastal Marshlands Protection Act of 1970 (O.C.G.A. § 12-5-280 et seq.) or to any area of isolated freshwater wetlands shall be issued in the absence of a variance granted by the mayor and council subject to the strict application hereof pursuant to section 5-090. In addition to those provisions of article V, chapter 22 of the City Code which may be applicable, it shall be unlawful for any person or entity to place in marsh, marshland, or coastal marshlands as so defined any material whatsoever, in the absence of a permit issued pursuant to a variance properly granted.

(L) Construction of docks, walkways, etc.; liability insurance. This subsection is intended to supplement and expressly not repeal existing provisions of Tybee’s Code of Ordinances relating to permits required for construction, relating to building permits, regarding wetlands protection, regarding beach dune or vegetation disturbance.

All those individuals engaged in the construction or repairs of docks, walkways, marinas or marine facilities, or any other structure on or over coastal marshlands as defined in O.C.G.A. § 12-5-282(3) shall, prior to the commencement of any such construction, preparation or work provide to the City of Tybee Island evidence of liability insurance and/or bonds and/or letters of credit specifically covering environmental and other damages. Such applicant shall also provide for coverage and/or bonds and/or letters of credit in the nature of a performance bond requiring the completion of the work if it is not performed in accordance with the anticipated completion schedule filed with the city and shall further include the cost of removal of any equipment, debris or materials of any nature not removed by the dockbuilder. When a bond or letter of credit is used for the purposes described herein such bond or letter of credit shall be issued to the benefit of either the City of Tybee Island or the owner of the property depending upon the circumstances and the building official of the city shall be authorized to determine to whom the bond or letter of credit should be payable.

The amount of insurance, bond, or letter of credit shall be based on the nature, scope and cost of the anticipated work and shall take into consideration the potential consequences of spills, removal of equipment, debris or materials and other risk and shall be in such amount as is set by the building official of the city or his designee.

Including but not limited to fuel spills, fires, submersions of equipment and building supplies, etc., all dockbuilders shall be required to report any accidents, casualties or events which occur in connection with activities provided for in this subsection and which are likely to cause damage or which may cause damage to property, persons, the environment or coastal marshlands and in no event shall the responsible party wait more than two hours after the occurrence of such event, casualty or occurrence.

Any violation of this subsection shall subject the offender to punishment under section 5-160.

(Ord. No. 2001-13, 7-12-2001; Ord. No. 2001-02, 1-11-2001; Ord. No. 2005-02, amended 4-11-2005; Ord. No. 2005-07, amended 3-3-2005; Ord. No. 2005-03, amended 3-3-2005; Ord.

No. 2005-02, amended 2-4-2005; Ord. No. 2004-16, amended 1-12-2005; Ord. No. 2004-16, amended 1-12-2005; Ord. No. 2004-16, amended 1-12-2005; Ord. No. 2001-13, amended 12-12-2001; Ord. No. 2001-02 Shore Protection, amended 4-19-2001; Ord. No. 1999-16, amended 6-4-1999; Ord. of 3-23-2006; Ord. of 1-11-2007(2); Ord. of 10-9-2008(3))

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:tybee-island/zoning/5-010@2026-11-11-c40da88ae3

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Tybee Island Zoning Ordinance, See. 5-010. Permits required for construction | Georgia Commons