Sec. 11.5. Certificate of occupancy required.
About this text
- As published by Municode, retrieved 2026-11-11
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
A certificate of occupancy issued by the building inspector is required in advance of occupancy or use of:
[1] A building hereafter erected;
[2] A building hereafter altered so as to affect the front, side or rear yards thereof or its height;
[3] A building or premises in which there is a change of use;
[4] A building moved from one location to a second location where that building will house persons or property.
[5] A building which has not been occupied within the preceding 12 months; or [6] Any nonconforming use that is existing at the time of enactment of this ordinance or an amendment thereto that is changed, extended, altered, or rebuilt thereafter. The certificate of occupancy shall state specifically where the nonconforming use fails to meet the provisions of the ordinance.
Within three working days after the application for a certificate of occupancy, a final inspection of the property in question shall be made.
The building inspector shall issue a certificate of occupancy if the building is found to conform to the provisions of this ordinance and if the final construction complied with the plans submitted for the building permit.
A record of all certificates shall be kept on file in the office of the building inspector and copies shall be furnished on request to any person having a proprietary or tenancy interest in the building or land involved.