--- title: Valdosta Zoning Ordinance, Sec. 8-8. Utilities collection: local-codes id: local-code:valdosta/zoning/8-8 cite_as: Valdosta, Ga., Zoning Ordinance § 8-8 canonical_url: https://georgiacommons.org/code/local/valdosta/zoning/8-8 md_url: https://georgiacommons.org/code/local/valdosta/zoning/8-8.md text_url: https://georgiacommons.org/code/local/valdosta/zoning/8-8/text source_url: https://library.municode.com/ga/valdosta/codes/code_of_ordinances date: 2026-11-11 status: active jurisdiction: city:valdosta jurisdiction_name: Valdosta place_fips: "1378800" corpus_version: local-codes-valdosta-1ea06aa7b7af publisher: Georgia Commons, an independent project of Georgia Civic Data. Not the State of Georgia. Not legal advice. up: https://georgiacommons.org/code/local/valdosta/zoning/~appendix-b.md previous: https://georgiacommons.org/code/local/valdosta/zoning/8-7.md next: https://georgiacommons.org/code/local/valdosta/zoning/8-9.md index: https://georgiacommons.org/code/local/valdosta.md branch: zoning edition: As published by Municode, retrieved 2026-11-11 edition_date_kind: retrieved source_publisher: Municode version_id: local-code:valdosta/zoning/8-8@2026-11-11-71baf711c9 --- # Valdosta Zoning Ordinance, Sec. 8-8. Utilities > As published by Municode, retrieved 2026-11-11 > The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included. Part of: Appendix B - SUBDIVISION REGULATIONS / 8 - MINIMUM IMPROVEMENTS The installation of utilities shall be as follows: 8-8.1. Communication Distribution Systems: All communication distribution systems installed solely for the purpose of extending communications service within a development and within the property limits of such development shall be placed underground except that this requirement may be waived by the planning commission in cases where undergrounding is not economically or technically feasible, see section 8-8.5 below. Incidental communication terminal boxes may be placed above ground. 8-8.2. Electric Power Distribution Systems: All electric distribution systems of 25,000 volts or less installed solely for the purpose of extending electric service to a development and within the property limits of such development shall be placed underground except that this requirement may be waived by the planning commission in cases where undergrounding is not economically or technically feasible, see section 8-8.5 below. 8-8.3. Easements: Developers shall allocate necessary easements with future maintenance access. 8-8.4. Location of Underground Installations: The plans submitted to the city engineer will set forth the anticipated location of all underground installations. 8-8.5. Feasibility Criteria: The following criteria will be used to determine whether or not underground installation is feasible. When installation is determined to be not feasible for either economic or technical reasons, the planning commission will authorize overhead installation. a. Communications Distribution Systems: Economic Feasibility—Undergrounding of electric facilities shall be deemed to be feasible if the cost to the utility is reasonably competitive to aerial construction. Technical Feasibility—In the absence of a showing that terrain, soil conditions, and other factors prevent proper installation and/or operation of underground facilities, underground facilities, undergrounding shall be deemed technically feasible. b. Electric Power Distribution Systems: Economic Feasibility—Undergrounding of electric facilities shall be deemed to be feasible if the charge levied by the utility on the developer, pursuant to a uniform policy of the utility or policy established by order of the Georgia Public Service Commission, is equal to or less than 25 percent of the cost borne by the utility in establishing such service. Technical Feasibility—In the absence of a showing that terrain, soil conditions, or other factors preventing proper installation and/or operation of undergrounding shall be deemed technically feasible.