Walnut Grove · Zoning Ordinance
Appendix A - ZONING / Article XIV - ADMINISTRATION, ENFORCEMENT, PENALTIES AND REMEDIES
Sec. 1404. Construction progress.
About this text
- As published by Municode, current through 2025-09-23
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
If no substantial construction progress has been made within six months of issuance of the building permit, the permit becomes invalid. The permit may be re-issued only upon completion of the application procedure outlined in sections 1401 and 1402.
Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.