Sec. 626. Inert and construction and demolition landfills.

About this text

  • As published by Municode, current through 2025-09-23
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

1. The following conditions must be met, except inert landfills only require a distance of one-half of each of the distance requirements listed below:

a. The location and boundaries of the site shall be surveyed and a plat and legal description provided to the city, together with other exhibits as required in this ordinance. The landfill shall have primary access via a state or federal highway or a paved road. All such operations shall be located on a road that does not create traffic through an area developed primarily for residential purposes. A stop sign shall be erected and maintained by the owner/operator at all egress roads from the landfill. Under no circumstances shall trucks use private drives or private access routes to or from the applicants' property that are within 300 feet of any residence.

b. A landfill shall only be permitted where all roads used for access have been built to a standard sufficient to withstand the projected number of trips per day at maximum weight for the vehicles expected. If a landfill is proposed adjacent to roads that are not sufficient to withstand the loads, or were not designed for such loads, the landfill owner must pay to bring such roads up to standard from the entrance of the landfill to the nearest county or state road of sufficient strength; or the landfill shall be denied. Truck traffic shall be restricted to roads of sufficient strength and width, with either a turning lane or four lanes.

c. To allow for an adequate buffer, the landfill shall be located on a parcel of land not less than 250 acres in size, and the landfill cell area (that is, holding actual waste) may not exceed 30 percent of the total acreage, with landfill operations areas (i.e., cells plus scales, offices, storage, other buildings, etc.) not exceeding 40 percent. No landfill cell may exceed 60 feet in height above the original natural grade, when fully filled, covered and vegetated. No more than ten acres of the property can be active landfill cell at any one time.

d. The proposed facility shall not be located within two miles of a significant groundwater recharge area nor within two miles upgradient of any water supply watershed nor within 1,000 feet of a wetland nor in the 100-year floodplain nor in seismic impact zones nor in unstable areas nor within 400 feet of a fault that has had displacement in Holocene time.

e. Such facility shall not be situated within two miles upgradient of any surface water intake for a public water drinking water source.

f. The applicant shall include with any rezoning application a report detailing the phasing of the landfill.

2. Such use shall also comply with the following regulations:

a. The landfill shall be suitably fenced to control access to the premises and to prevent the spread of materials. All landfill cell areas and landfill operations areas must be surrounded by a chain-link fence at least eight feet high, topped with three strands of barbed wire, angled 45 degrees toward the outside of the premises at the top. All entrances shall have an eight-foot-high gate, which shall be closed and locked at all times that the landfill is not open.

b. Upon final closure of the landfill, the site shall be left in a stabilized and vegetated condition in accordance with a post closure plan approved by the Georgia department of natural resources. Furthermore, the reclamation plan for the closed landfill shall be submitted to the city and be subject to approval by the mayor and council. The plan shall propose reclamation or redevelopment that will best serve the needs and interests of the citizens of the city. Reclamation or redevelopment shall be accomplished as soon as practicable following closure of any areas of the landfill. Substantial completion of reclamation or redevelopment shall be effected within two years after termination of the waste disposal facility. Inactivity for six consecutive months shall constitute, for this purpose, termination of disposal activities.

c. Materials placed in landfills shall be compacted to the extent possible with available equipment and covered with earth at least monthly or more frequently as may be required to meet industry standards.

d. The disposal site shall be graded and drained to minimize runoff onto and from the landfill surface, to prevent erosion and to drain water from the surface of the landfill.

e. All-weather access roads shall be provided to the disposal site and provisions shall be made for waste moving and grading equipment repair or replacement when needed within a reasonable period of time.

f. The applicant shall follow all applicable federal and state laws and city regulations so as to prevent air, land and water pollution, public health hazards or nuisances.

g. Suitable means shall be provided to prevent and control fires, including sufficient dirt stockpiled near the active cell to extinguish fires.

h. Rodents and insects shall be controlled to meet industry standards.

i. The applicant shall submit to the city the design and operation plans of the landfill facility once they are approved by the State of Georgia. All landfills shall be double composite lined, designed and installed under the supervision of a licensed professional engineer, with a leak detection system between the two liners, and leachate collection per EPA subtitle D. However, inert landfills shall only require one such composite liner.

j. A minimum 400-foot natural, undisturbed buffer shall be provided between all active waste burial areas and exterior property lines except for approved perpendicular access and utility crossings. The buffer must be sufficiently vegetated to be completely opaque and prevent viewing of any landfill cell at all times of the year. If the preexisting natural buffer is insufficient, the buffer shall be enhanced with a berm of at least ten feet in height and 50 feet wide at the top and plantings of evergreen trees, not more than ten feet apart, or evergreen shrubbery not more than five feet apart, in staggered rows, on the berm, parallel to the boundaries of the property. Evergreens shall be at least two-year transplants at the time of planting, shall grow to not less than ten feet in height within two years or less, and shall be sufficiently spaced to provide effective sight barriers when ten feet in height. Trees or shrubs that die must be promptly replaced with the same type tree that will grow to at least ten feet high within two years.

k. The waste disposal boundary of any landfill or lateral expansion of an existing landfill shall not be located within 1,000 feet of any occupied dwelling. Any security lighting deemed necessary by the owner/operator shall be the sodium vapor type and shall be aligned so that no part of the illuminated field falls on adjacent property.

l. A minimum 75-foot natural, undisturbed buffer shall be provided between non-waste disposal operations and exterior property lines except for approved perpendicular access and utility crossings.

m. The limits of any 100-year floodplain or a stream buffer of 500 feet, whichever is greater, shall be preserved as natural, undisturbed area except for approved perpendicular access and utility crossings.

n. No disposal area shall interfere with the established natural flow of surface waters to the detriment or damage to adjoining public or private properties. The mayor and council shall have the right to require an applicant to construct adequate sediment basins if it appears that substantial water or sediment may be carried into any nearby property or state waters.

o. Sufficient setback shall be provided from all property lines and public highways to assure adequate lateral support for the maintenance of adjacent public and private property. No disposal area shall be permitted closer than 400 feet from the interior boundary lines. Disposal areas shall at no time be permitted where adjoining lateral support for the maintenance of adjoining land is not maintained.

p. Hours of operation of any landfill shall be no greater than 7:00 a.m. to 6:00 p.m. Monday to Friday. No operation is allowed on Saturday or Sunday. A sign clearly indicating the hours of operation and prohibiting dumping at all other times shall be placed in a conspicuous location at the entrance. Disposal facilities shall have qualified personnel on duty at all times to direct the dumping, spreading, compaction, and covering of materials. All such personnel shall reside in close enough proximity to respond in the event of a fire.

q. All litter shall be collected from the landfill site by the end of each working day and either placed in the fill, compacted and covered that day, or stored in a covered container.

r. Any landfill shall be open to use by residents, property owners, and businesses, during established business hours, at a rate to be agreed upon by the mayor and council. Special handling fees may be charged for bulky or difficult to process items.

s. A mitigation trust fund shall be established at a bank within the city chosen by the mayor and council. The operator shall pay $5.00 per ton of waste disposed into this trust fund for the life of the landfill. Expenditures from the trust fund are to be approved by a committee consisting of one citizen appointment by the mayor and council, the mayor, and one representative of the owner/operator. Funds may be used, without limitation, for off-site litter control, groundwater and surface water monitoring, provision of alternative water supplies, and payments to adjacent property owners and others, at the discretion of the committee, for damages caused as a result of the landfill or its related operations. The trust fund shall exist and earn interest for 90 years following the expiration of the post-closure period, and at that time the remaining funds shall be paid to the owner/operator or its successor or assigns.

3. Further requirements.

a. Each person proposing to locate a solid waste management facility in the city shall submit an application for a letter of assurance demonstrating compliance with the provisions contained in this ordinance and consistency with the city solid waste management plan. Before the applicant identifies a potential site and conducts a hydrological study for submission to the environmental protection division for site suitability, the applicant shall notify the local government and participate in a public meeting to discuss the waste management needs of the local government, to describe the siting process to be followed, and to allow for public input. The local government shall give notice of the meeting published in a newspaper of general circulation at least twice per week for two weeks immediately preceding the date of the meeting. The cost of publication shall be the applicant's responsibility.

b. Each person proposing to locate a solid waste management facility in the city shall submit an application compliant with this ordinance and the city solid waste management plan and the city solid waste management facility ordinance.

c. Within 45 days of the submission of the application, the mayor and council shall hold a public hearing so that the applicant can present his plans and answer questions regarding the same. The applicant shall be required to pay for notice to be published at least twice in the county legal organ prior to the hearing. Notice shall be published beginning at least 15 but not more than 45 days prior to the date of the hearing. The notice shall state the time, place, and purpose of the hearing. Copies of all ads or a certification from the publisher must be submitted to the city prior to each hearing.

d. The mayor and council shall require an application fee in the amount of $5,000.00 to $25,000.00 to reimburse the city for the costs of any needed professional assistance that may be required to evaluate the application and amendments, verify its contents and evaluate the impact of such a facility on the community, public health and environment. This assistance may include, but shall not be limited to, the assistance of lawyers, biologists, geologists, engineers, chemists, hydrologists, emergency response, transportation and public health experts, land appraisers and professional testing laboratories. Funds not so expended in the legitimate review of the application shall be returned to the applicant. Failure to provide these funds within 30 days of demand shall result in termination of the application process or cancellation of the letter of assurance. The mayor and council may take legal action against the applicant for any costs incurred to the city up to the point of termination.

e. The applicant shall submit to the city 12 copies of all information required by federal and state agencies for the facility for which it requests a city permit at the time such information is submitted to the state and federal government. The review procedure shall not begin nor shall the application be designated as complete until such time as all required data are submitted and the appropriate fees are paid, or suitable arrangements for payment have been approved by the mayor and council.

f. Once a completed application is submitted to the city, the applicant shall be required to send a letter via first class mail to all adjoining property owners, as shown on the tax records of the city on the date of the application, and to all property owners where any portion of their property is within 1,000 feet of the boundary of the facility. This notice shall be required to state that the applicant is seeking a letter of assurance for a solid waste management facility. Certification of this notice must be provided to the mayor and council, along with a list of all owners prior to the public meeting for public comment on the completed application.

g. The mayor and council, before deciding whether to approve the application or to accept it with modifications, shall determine if such facility complies with the location standards and is consistent with the city solid waste management plan including the solid waste management facility ordinance, using as criteria and standards those set forth in the city solid waste management plan including the solid waste management facility ordinance. If approved, the mayor and council shall issue a letter of assurance as required by state law and regulations.

h. Any proposal shall be specifically conditioned to the site plan, maps, elevation renderings, and other detailed plans to insure that the development is erected in accordance with the presented materials. The approval may also impose additional conditions, if the conditions are designed to minimize the impact of the use on the neighboring property, streets, and so forth.

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:walnut-grove/zoning/626@2025-09-23-d6d6279566

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Walnut Grove Zoning Ordinance, Sec. 626. Inert and construction and demolition landfills | Georgia Commons