Sec. 3.1. General procedure.

About this text

  • As published by Municode, retrieved 2026-11-11
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

1. No land disturbing activity of any kind shall begin on any land subject to these regulations without prior approval of the preliminary plat and construction plans as described hereinbelow, and in the zoning ordinance.

2. Before any land is subdivided the owner of the property proposed, or his authorized agency, shall apply for and secure approval per the following procedures:

i. Sketch plat and conceptual layout.

ii. Preliminary plat.

Types of Yards iii. Development permit approving the construction plans.

iv. Final subdivision plat.

Multi-family, commercial and industrial subdivisions shall comply with these regulations.

The sketch plat and conceptual layout requirements are as follows: 24-inch by 36-inch sketch plat and concept plans for review by the mayor and council are required prior to formal initiation of the preliminary plat process. The sketch plat and conceptual layout shall be prepared per accepted professional standards. The mayor and council shall review the sketch plat and conceptual layout within 30 days of submission by the developer. The developer will be notified at least seven days in advance of the date and time of the mayor and council's review of these items.

The developer shall attend the meeting and be prepared to discuss the sketch plat and conceptual layout with the mayor and council. The purpose thereof is to save time and expense in reaching general agreement as to the form of the plat and the substance and parameters of the construction plans and the objectives of these regulations.

Items to be addressed in the preliminary plat and the construction plans include as follows:

Compliance with zoning and subdivision and tree regulations, lot footprint and layout, building size, building layout and design (including design details that may help increase marketability and conformity with nearby structures), facade type (for example, masonry construction), building height, flood prevention, paving, curb and sidewalk, utilities, temporary structures, greenspace, recreational amenities, front entrance construction, maximum number and/or density of units, water and sewer lines and water and sewer connections, tree protection, stormwater detention, owners association and restrictive covenants, street lights, street signs, fencing, and vegetative buffer.

Promises and representations made by the developer in the sketch plat and conceptual layout are binding on the developer. The mayor and council shall approve, approve with conditions, or reject the sketch plat and conceptual layout, utilizing the standards and criteria of the subdivision regulations and of the city zoning ordinance. The sketch plat and concept plans shall establish the parameters for the preliminary plat, construction plans and final plat, and the developer shall not depart from these parameters. Approval of the sketch plat and conceptual layout does not constitute approval of the preliminary plat, construction plans or final plat. Nor does it establish any vested rights.

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:watkinsville/zoning/3.1@2026-11-11-60adea740f

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Watkinsville Zoning Ordinance, Sec. 3.1. General procedure | Georgia Commons