Sec. 5.18. Overview—Project construction.

About this text

  • As published by Municode, retrieved 2026-11-11
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

All improvements shall conform to standard specifications as set forth in these regulations and in the applicable regulations of the city, and/or other state and federal regulations. In case of conflict, the more stringent standards shall apply.

1. Responsibility during construction.

a. The developer and his/her design professional of record have full responsibility for quality control and inspection during construction to ensure substantial conformance with the approved construction plans, city standards, city regulations, and generally accepted construction practices. City and county personnel are only providing construction observation to intermittently check the adequacy of the developer's quality control and inspection.

b. Any construction issues requiring an interpretation and/or change in the plans, standards, and/or regulations are to be resolved by the design professional of record and presented to the city engineer for written concurrence or approval. Any design changes must be revised on the construction plans and issued as a change to the approved construction plans.

c. Failure of the developer to provide adequate quality control and inspection which results in a substantial nonconformance with the plans, standards, regulations or generally accept construction practice or endanger the public health, safety, and welfare shall be cause for the city engineer or city manager or his/her designee to issue a stop work order for any or all portion(s) of the construction in accordance with city procedures and ordinances. The order will remain in effect until the developer or his/her design professional of record can demonstrate to the city that adequate quality control and inspection will be provided to address and correct the nonconformance and minimize the potential for further nonconformance issues or endangerment issues.

d. Each day of continued construction on the scope of work covered by the stop work order under these regulations shall be considered a separate violation.

e. The developer controls the means, sequence, and methods of construction. As such, the developer has full responsibility for safety on the project site and compliance with all federal, state, and local regulations pertaining to safety and environmental requirements.

f. Preconstruction activity. Following the issuance of any permit authorizing clearing and grading of a site, areas required to be undisturbed, such as natural landscape buffers or stream buffers, must be designated by survey stakes, flags, ribbon, or other appropriate markings and shall be inspected and approved by the city engineer and city manager or his/her designee prior to the commencement of any clearing or grading activities.

g. Grading.

(1) Grading shall be done in accordance with the lines and grades drawn on the approved grading plan.

(2) Required erosion and sedimentation control measures and stormwater drainage facilities are to be installed in accordance with the approved plans as development progresses.

2. Development phase inspections. Requests for inspections shall be made by the owner or contractor to the code compliance officer in accordance with the listing of inspection responsibilities established by the city. Such requests shall be made at least 24 hours prior to when the inspection is needed. Inspections shall be made and passed prior to continuation of further activity or proceeding into new phases. Inspections are required of each of the following phases, as applicable to the actual work to be performed under the development permit:

a. Prior to clearing or clearing and grubbing of the property or any portion included under the development permit, inspection of erosion and sedimentation control measures and protective devices for undisturbed areas. Inspection of erosion and sedimentation control measures will be conducted on a continuing basis.

b. Upon completion of street grading, inspection and approval shall be required prior to trenching or continuation with subgrade preparation.

c. Upon installation of storm drainage pipe, detention, or other stormwater facilities.

d. Street curbing and gutter (if provided). Inspection shall be requested after the forms or string line have been set. Street width and vertical and horizontal alignment may be spot-checked.

e. Sub-grade of streets. The sub-grade may be roll tested in accordance with these regulations.

f. Street base. The base may be string-lined for depth and crown. The street base will be tested for depth and compaction in accordance with these regulations, and may be roll-tested in accordance with these regulations, at the discretion of the city engineer.

g. Paving. The code compliance officer and/or the city engineer may be on site during the paving process to check consistency, depth, and workmanship, as applicable. For asphalt paving, the temperature of the material will be monitored, the asphalt will be tested for depth and compaction in accordance with these regulations, and may be roll-tested in accordance with these regulations, at the discretion of the city engineer and the city manager or his/her designee.

3. As-built data.

a. Upon completion of the development activity as authorized by the development permit and prior to final development inspection of public and private improvements, the owner shall submit to the code compliance officer for distribution to the city engineer and the city manager or his/her designee, as appropriate, for review and approval a complete set of record drawings showing "as-built" conditions prepared by the design professional of record who prepared the original plans, or a professional land surveyor, engineer or landscape architect licensed in the state. These drawings shall show the location of:

(1) Street centerlines and rights-of-way lines.

(2) Drainage system pipes, manholes and channels, including finished elevations.

(3) Stormwater detention facilities including finished elevations.

(4) Sanitary sewer system (if any) including finished elevations.

(5) Water system and reuse water system (if any) including finished elevations.

b. The as-built data shall be certified and sealed by the design professional of record or other professional preparer, subject to the tolerances of accuracy indicated in the certification.

4. Final development inspection.

a. Following submission and review of the as-built data, the code compliance officer and city engineer shall conduct a final development inspection of the project.

b. The owner shall be responsible for correcting any deficiencies identified in the final development inspection prior to approval of a final subdivision plat.

History

The history line the source prints at the end of the section.

(Amd. of 9-21-2022)

Read this code where it is posted (Municode) The source is the city's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:watkinsville/zoning/5.18@2026-11-11-0a8fdd3536

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Watkinsville Zoning Ordinance, Sec. 5.18. Overview—Project construction | Georgia Commons