1. Permit for utility installation. This section governs the installation of telephone lines, gas lines, water lines, sanitary sewer lines, gray-water reuse lines, electrical lines, fuel lines, steam lines, T.V. cables, open storm drainage, storm sewers, and other utilities within city-maintained road or street rights-ofway. a. Application for permit; when required. (1) New facilities or extensions of existing facilities within city or county-maintained road or street rights-of-way shall require a written application and a permit issued by the appropriate department. (2) Service lines and maintenance and repair of existing facilities shall not require a permit unless a pavement cut is required, but all other requirements of these regulations shall apply to said activities, where applicable. (3) Emergency cuts without a permit may be made when required. Such cuts shall be followed by a written application or report to the city engineer and utilities coordinator within two working days thereafter. Repairs to the pavement and disturbed soil and all other applicable requirements of these regulations shall apply to such emergency cuts. b. Application for permit; requirements. Application for permit for utility facility installation shall be made to the county utilities coordinator. (1) In the case of water lines and sanitary sewer lines, the applicant must submit four copies of a plan showing the proposed installation to the utilities coordinator. Said plans shall be approved or denied, or additional information shall be requested, within 30 days or said plans shall be deemed to have been approved. (2) A request for breaking of pavement must be described in detail in the application. (3) in those cases where a state department of transportation application and permit is required, a copy of the department of transportation application and permit along with the expected date of work commencement shall be provided to the county utilities coordinator and said copy shall satisfy the application and permit requirements herein. c. Installation and construction requirements. (1) The installation of said facility as authorized shall be subject to the inspection, direction and control of the city and the county's engineer or utilities department (as appropriate) who shall be notified before work is commenced. Such notification shall include the date and time of the commencement of the construction and/or installation and location of same. (2) The work shall be performed in a workmanlike manner and all installations shall be done by the utility owner in such a way as to leave free flows in drainage ditches, pipes, culverts or other surface water drainage facilities of the roadway or its connections. No part of any installation shall be attached to any portion of a bridge, culvert or other structure of the roadway without special authorization of the city engineer after detailed information is furnished as may be required. (3) Where breaking of pavement has been approved, a six-inch concrete slab will be poured over the backfilled trench and will rest on undisturbed soil. If the pavement is asphalt, the surface of the six-inch, concrete slab will be 1½ inches below the surface of the abutting pavement. The 1½-inch section will be paved with type E, F, or H plant asphalt. The finished surface will be smooth and flush with abutting pavement. (4) Underground piping and wiring will be installed and located in accordance with these regulations. Where underground piping parallels the roadway the excavated ditch edge nearest the pavement will be at least eight feet from the pavement edge, unless otherwise authorized herein. (5) The facility trench shall be backfilled carefully after the facility has been installed, in accordance with the standard practice for installing culverts and minor structures. In crossing roadways the backfill will be made in six-inch layers and each layer firmly compacted. Where roadway grass is disturbed, satisfactory replacement will be accomplished including adequate seeding of new grass. (6) The full and entire expense and cost of the facility installation and maintenance shall be borne by the utility owner and the utility owner shall make necessary arrangements for traffic over said point during such work as may be directed by the city engineer. The utility owner shall place the necessary barricades, warning signs, signals, lights and, if necessary, watchmen for the protection of the traveling public, and further agrees by the acceptance of the permit to keep and hold the city and the county harmless from any and all damages caused by negligence on the part of the utility owner, its agents, servants, officers or employees, or contractors, engaged in doing said work, or any injuries or damages suffered by anyone as a result thereof. d. Future relocations at utility expense. In case the mayor and council should in the future decide to widen and/or relocate the existing road, they reserve the right to require the utility owner to take up and relay such sections of the facility within the right-of-way as may be necessary to take up and relay from an engineering standpoint due to such widening and/or relocating; the taking up and relaying to be at the expense of the utility owner. This work shall be completed within 60 working days after notification by the mayor and council or within such other time as may be approved in writing by the city engineer or designated representative of the city. 2. Additional design and construction considerations. More stringent design and construction standards may be required by the city engineer where streets cross 100-year flood plain(s), serve as the only means of public ingress and egress to one or more lots, cross flowing streams, cross poor soils or encounter other similar conditions. a. General. All streets, roads, and alleys shall be constructed to provide the necessary paving, roadway, drainage, and safety requirements as provided herein and by other specifications of the city. b. Clearing and grubbing. (1) All streets, roads and alleys shall be graded to their full width so that pavement, shoulders and sidewalks, where required or proposed for future installation, can be constructed on a uniform plane. The right-of-way shall be cleared of all trees. Additional trees shall be removed outside of the right-of-way if the area under the dripline of the tree in the right-of-way is disturbed, as directed by the city engineer or code compliance officer. (2) Clearing, grading or other land disturbing activities associated with subdivision construction shall not commence until the preliminary plat, engineered construction plans and soil erosion/sediment control plans have all been approved by the city. This shall not be construed to prohibit necessary logging or survey operations prior to approval of such plans. c. Storm drainage. See the erosion control and stormwater management article of these regulations for requirements relating to storm drainage. 3. Installation of utilities; general. All utility crossings, service lines, conduit, or other related appurtenances shall be installed within the limits of the roadbed plus two feet of each side of the pavement surface, prior to the placement and compaction of the graded aggregate base course. Utilities should be installed following the installation of curb and gutter, unless the curb line is accurately staked at 50-foot intervals to ensure proper utility locations as specified herein. The developer shall coordinate the location of all utilities and provide a copy of all as-built and proposed locations at final plat. 4. Slopes and shoulder improvements. Slopes and shoulder improvements shall conform to the requirements hereof. 5. Construction methods; roadways. a. Roadway grading and embankments. (1) All streets and roads shall be graded to their full width by the sub-divider so that pavements and sidewalks, where required or proposed for future installation, can be constructed on a level plane as shown in the cross-sections on the approved plans. (2) The entire area within the typical grading section shall be cleared and grubbed of all trees, bushes, stumps and debris. Such debris shall be disposed of in a lawful manner, and shall not be buried in the right-of-way or within the project limits. (3) Road fill of suitable material free of organic matter shall be placed in uniform eight-inch layers compacted to at least 95 percent of maximum density throughout as specified for construction and testing in the Georgia DOT standards for embankments. Embankment compaction test shall be taken at an interval not exceeding 2500 cubic yards. All storm drainage and other underground utilities installed under the roadbed and the backfill in all ditches shall be compacted to at least 95 percent maximum density. Compaction testing of backfill for said structures shall be taken at a minimum interval not less than one between any two structures. Compaction test results shall be reported to the city immediately after results are obtained. (4) Cut and fill slope ratios shall start at the edge of the right-of-way and shall not exceed 3:1 in the right-of-way and 2:1 outside of the right-of-way. In lieu of a cut or fill slope, a retaining wall may be utilized where necessary with the approval of the city. (5) Cut or fill slopes shall be uniform for each section of cut or fill. The depth of cut or fill shall be constructed to the maximum cut or fill occurring in any one section. When a cut made in rock requires blasting, the slope may be changed to an alternative slope grade upon written approval of the city. (6) If paving is to be delayed, provisions shall be made to drain low points in the roadway. If curbing has not been installed, a break in the berm section may be provided. If curbing is in place, four-inch pipe sections shall be used to provide drainage under the curb to side slopes. (7) All work must be approved by the city prior to preparation of the subgrade. It is the design professional's duty to inspect that road grading specifications has been met. The developer will provide to the city a statement of inspection completed by a registered professional engineer, licensed by the state, that all construction requirements have been met for roadway grading. The developer shall also provide certification to the city by a professional land surveyor or engineer licensed in the state that grading has been completed to the lines and grades to a tolerance of +/- six inches. The developer will also provide staking of the roadway centerline in conjunction with said certification for verification by the city engineer and code compliance officer. Upon presentment and approval of such documentation by the city engineer, road construction may continue. b. Preparation of subgrade. (1) All boulders, organic material, soft clay, spongy material and any other objectionable material shall be removed and replaced with approved material. The subgrade shall be properly shaped, rolled and uniformly compacted to conform with the lines, grades and typical cross-sections as shown on the drawings approved by the city. (2) The subgrade shall be scarified to a depth of eight inches, and compacted to 95 percent maximum dry density and within +/- three percent of the optimum moisture content. Subgrade compaction shall be determined by field testing at intervals not to exceed 1,500 feet. Compaction testing shall be accomplished in accordance with the standardized testing protocols of GDOT. Written test results shall be provided to the city engineer immediately after results are obtained. (3) It is the design professional's duty to inspect that subgrade preparation specifications have been met. The developer will provide to the city a statement of inspection completed by a registered professional engineer, licensed by the state, that all construction requirements have been met for roadway subgrade preparation. Upon presentation and approval of such documentation by the city engineer, roadway construction may continue. c. Preparation of aggregate base course. (1) All base course material shall be deposited and spread by means of spreader boxes, or approved mechanical equipment, or from moving vehicles equipped to distribute the material in a uniform layer. (2) Immediately following the spreading of the coarse aggregate, all material placed shall be compacted to the full width by rolling with a smooth wheel power roller of adequate size and weight to achieve compaction. (3) Any irregularities, areas of segregation, or depressions that develop under such rolling shall be corrected by loosening the material at these places and adding or removing material until the surface is smooth and uniform. The application of water, applied uniformly over the base course, may be required to achieve adequate compaction. Shaping and rolling shall be performed alternately as required to maintain a uniform compacted base until a surface or treatment has been applied to the base. Along curbs, headers and walls and at all places not accessible to the roller, the base course material shall be tamped thoroughly with mechanical tampers or approved hand tampers. (4) Graded aggregate base shall meet the requirements of Georgia DOT specifications for graded aggregate. Graded aggregate base compaction test shall be taken at an interval not exceeding one per 1,500 linear feet. No graded aggregated base shall be placed on muddy or frozen subgrade. The moisture content of the graded aggregate base shall be uniformly distributed and shall be adequate to allow compaction to the specified density. After the material placed has been shaped to line, grade and cross section, it shall be rolled until the course has been uniformly compacted to at least 100 percent of the maximum dry density when Group 2 aggregate is used, or to at least 98 percent of maximum dry density when Group 1 aggregate is used. The theoretical maximum dry density shall be established using the appropriate test methods of the Georgia DOT Sampling, Testing and Inspection Manual. Moisture content shall be within +/- 3 percent of the optimum content. Compaction test results shall be reported to the city engineer immediately after results are obtained. (5) After the base course has been installed and inspected, and before any surface is applied, all residential streets shall be primed with suitable asphaltic materials as per Georgia DOT Specification 412 unless asphalt paving commences within two weeks from acceptance of the certification from the period March 1 to December 1 or within 24 hours during the period December 1 to March 1. (6) It is the design professional's duty to inspect that graded aggregate base course preparation specifications have been met. The developer will provide to the city a statement of inspection completed by a registered professional engineer, licensed by the state, that all construction requirements have been met for roadway graded aggregate base course preparation. Upon presentation and approval of such documentation by the city engineer, roadway construction may continue. d. Asphaltic concrete construction. (1) Paving material shall consist of a conventional bituminous plant mix. The use of "Superpave" mix design will be permitted. Recycled asphalt products (RAP) will not be permitted for initial construction of roadways. RAP may be used in the binder course but only with prior approval of the city engineer and the code compliance officer. (2) Material, equipment, seasonal and weather limitations, preparation of road surface, material application and construction methods shall be the same as set out in the Georgia Department of Transportation's Standard Specifications for Road and Bridges, latest edition, and any amendments thereto. (3) Mix design(s) shall be provided to the city engineer for approval at least a minimum of two weeks prior to paving operations. (4) If paving will not be completed within two weeks after the base course is completed during the period March 1 to December 1, then, the base will need to be primed in accordance with GDOT Standards with the roadway being barricaded thereafter. The above will be required within 24 hours during the period of December 1 through March 1. (5) One asphaltic concrete extraction test per type mix shall be taken per subdivision. Extraction test results shall be reported to the city immediately after results are obtained. (6) Asphaltic concrete compaction test for each type mix shall be taken at an interval not exceeding one per 1,000 linear feet per one lane of roadway. All asphalt courses shall be compacted to no less than 95.5 percent of the target density. Compaction ranges of 95.4 percent to 93.4 percent will require a specific and separate three-year maintenance bond in the amount of 20 percent of the paving costs for the street affected. Compaction less than 93.4 percent will be cause for rejection and rework of the street section affected. The maximum pavement mean air voids will not exceed 7.8 percent in any instance. CompacAPPENDIX C—SUBDIVISIONS § 5.21 tion testing shall be accomplished in accordance with the appropriate standardized protocols for the GDOT Sampling, Testing, and Inspection Manual. Compaction test results shall be reported to the city immediately after results are obtained. (7) Where a binder course is provided on streets, a tack coat shall be applied to all prepared road surfaces as provided in Georgia DOT Specifications. (8) On streets where a binder course is provided, the final layer of asphalt shall be placed no later than one year after the binder course is laid or when 80 percent of the project is built-out whichever comes first. (9) The city engineer shall require that all work meet or exceed the above requirements. (10) It is the design professional's duty to inspect that the roadway asphaltic concrete construction specifications have been met. The developer will provide to the city a statement of inspection completed by a registered professional engineer, licensed by the state, that all construction requirements have been met for roadway asphaltic concrete construction. Upon presentation and approval of such documentation by the city, roadway construction will be considered as complete for the purpose of final plat. e. Base, asphalt and compaction testing. (1) Depth testing. The city engineer reserves the right to require depth checks on base materials and asphalt cores shall be taken at random locations at 500-foot intervals along each road at the discretion of the city engineer or the code compliance officer. Any area found deficient shall be brought up to the required thickness prior to placing any additional layer of material. All asphalt core holes shall be filled with hot mix asphalt of similar grade prior to final acceptance. (2) Additional testing requirements/coordination. All testing shall be scheduled with the city engineer and the code compliance officer, or his/her duly appointed representative no less than 24 hours in advance. Compaction testing shall not be performed until the surface/ material is to the lines and grades shown on the plans. Once an embankment, subgrade, or base course has been certified then that material shall not be disturbed or additional testing will be required. All areas or sections of the subgrade and base course, which do not pass compaction testing, shall be corrected. Once the developer makes all necessary corrections, it shall be his/her responsibility to schedule any and all subsequent test. The city engineer and the code compliance officer may require that in addition to the compaction testing required, a roll test be performed in accordance with these regulations. All certifications provided shall contain all test data and results to support certification. f. Seasonal limits. No roadway construction material shall be deposited or shaped when the subgrade is frozen at any depth or thawing at any depth or during unfavorable weather conditions including rain of any intensity. Paving material installation shall be subject to temperature and weather conditions as contained in Georgia DOT construction standards. The time period from December 1 to March 1 will require special construction procedures unique to the individual sites and weather conditions. The contractor/developer shall consult with the city engineer and the code compliance officer during a supplemental pre-construction conference prior to beginning or continuing any roadway construction work during this period. It shall be the responsibility of the developer to schedule this conference.