1. Removal and relocation of utility facilities.
a. Any utility using any part of a public road right-of-way or easement shall remove and relocate its facility when, in the reasonable opinion of the city, the facility constitutes an obstruction or interference with the use or safe operation of such road or when, in the reasonable opinion of the city, the facility will interfere with construction or maintenance.
b. When the city reasonably determines it necessary to have a utility facility removed and relocated, the city shall give the utility at least 60 days' written notice directing the removal and relocation of such utility obstruction. If the utility does not thereafter begin removal within a reasonable time sufficient to allow for engineering and other procedures reasonably necessary to the removal and relocation of the utility facility, the city may give the utility a final notice directing such removal shall commence within ten days from receipt of such final notice. If such utility does not, within ten days from receipt of such final notice, begin to remove or relocate the facility or fails to complete the removal or relocation within a reasonable time, the city may remove or relocate the same, and the expenses of such removal or relocation may be paid and collected as provided herein.
2. Replacement right-of-way for relocated utility.
a. When a public road improvement necessitates the acquisition of a utility's privately owned rights-of-way and the relocation of such utility's facilities, the city may, with written consent of the utility, provide a replacement right-of-way.
b. Whenever a public road improvement requires the relocation of a utility occupying public road rights-of-way, the city may, at the written request of such utility, provide to the utility a right-of-way which is not on public road right-of-way. In this event, the utility shall reimburse the city for the acquisition costs.
c. Title to property acquired for utility relocations may be transferred to such utility. However, the procedures for sale of property shall not be applicable to the transfer of property acquired for utility relocation. Any such property transfer to the utility shall be conveyed by the execution of a quitclaim deed.
3. Payment of expenses of removal and relocation of utility facilities. The expenses incurred by the city as a result of utility removal and relocation, including the cost of acquiring new land or interest therein, shall be paid out of the available appropriations of the city for the construction or maintenance of public roads. A statement of such expenses shall be submitted to the utility, which shall make payment to the city. In the event the utility does not make payment or arrange to make payment to the city within 60 days, the city shall certify the amount for collection to the city attorney. Nothing in this article shall be construed so as to deprive any utility, relocated from a location in which it owned a property interest, of compensation for such property interest.
4. Promulgation of regulations.
a. The State of Georgia, Department of Transportation, Utility Accommodation Policy and Standard, most recent edition, is adopted as the rules and regulations of the city with the following exceptions:
(1) Section 3.2(a) Where to apply is deleted and adopted in lieu thereof is the following "Applications for utility encroachment permits shall be made at Watkinsville, Oconee County, Georgia at the Office of the City Clerk."
(2) Section 3.2(b) Authority to Approve is deleted and adopted in lieu thereof is the following "The city engineer shall have full authority to approve requests for utility encroachment permits."
(3) Section 3.9(c) Notice to Other Utilities is deleted and adopted in lieu thereof is the following: Applicants shall comply with "Blasting or Excavations Near Underground Gas Pipe and Utility Facilities" Chapter of Georgia Code Ann. (O.C.G.A. § 25-9-1 et seq.).
(4) Appendix A, B, and C are deleted.
(5) The rules and regulations adopted are those used by the state. Wherever in the course of using or interpreting such rules and regulations, reference is made to the state, the DOT or other state department, officer or employee, same shall be interpreted to refer to the analogous city department, officer or employee, i.e., a reference to the state shall be interpreted to mean the city, a reference to the DOT shall be read to mean the city engineer or a reference to a state road shall be generally read to mean county or city road.