Channel protection shall be provided for each discharge point from the site unless meeting the exemption criteria outlined below. Channel protection shall be accomplished by providing for 24-hour extended detention of the 1-year, 24-hour storm event. Channel protection shall not be required if one of the following criteria is applicable to an outfall point on the site: • Point discharges that do not exceed two cubic feet per second for the 1-year, 24-hour storm in a post developed condition. • Sheet flow discharges that do not have more than 100 feet of contributing drainage area assuming that no impervious surfaces are within the contributing drainage area. • Point or sheet flow discharges from drainage areas consisting entirely of undisturbed lands on the site. • Point discharges which drain directly to a piped drainage system and which the county engineer has determined that the outfall of the system will not experience significant channel erosion as a result of not providing channel protection via extended detention of the 1-year, 24-hour storm. • Point discharges which drain directly to streams, rivers, wetlands, lakes or other scenarios where reduction of the 1-year, 24-hour storm will in the opinion of the county engineer result in no impact to downstream channel integrity.