Channel protection shall be provided for each discharge point from the disturbed portion site unless meeting the exemption criteria outlined below. Channel protection shall be accomplished by providing for 24-hour extended detention of the runoff from the disturbed portion of the site for the 1-year, 24-hour storm event. Channel protection shall not be required if one of the following criteria is applicable to an outfall point on the site: • Point discharges that do not exceed two cubic feet per second for the 1-year, 24-hour storm. • Sheet flow discharges that do not have more than 100 feet of contributing drainage area assuming that no impervious surfaces are within the contributing drainage area. • Point discharges which drain directly to a piped drainage system and which the county engineer has determined that the outfall of the system will not experience significant channel erosion as a result of not providing channel protection via extended detention of the 1-year, 24-hour storm. • Point discharges which drain directly to streams, rivers, wetlands, lakes or other scenarios where reduction of the 1-year, 24-hour storm will in the opinion of the county engineer result in no impact to downstream channel integrity. 2.5. Energy Dissipation. Energy dissipation shall be employed whenever the velocity of flows leaving a new stormwater facility exceeds the erosion velocity of the downstream area. 3. APPROVED CONSTRUCTION MATERIALS AND BMPS