The following outlines the process for developing a stormwater management plan as required for issuance and maintenance of site development permit in Whitfield County, City of Dalton, City of Tunnel Hill, and the City of Varnell. Pre-Design Phase Step 1. Check for new special district requirements with county engineer. Step 2. Check for concept plan submittal requirements. Concept plan is strongly recommended. Step 3. Prepare concept plan (if required). Step 4. Submit concept plan to county engineer and schedule concept plan meeting (if required). Step 5. Meet with county engineer to discuss concept plan (if required). Design Phase Step 6. Prepare stormwater management plan. Step 7. Submit stormwater management plan to county engineer for approval. Step 8. Execute stormwater inspection and maintenance agreement for all private on-site stormwater management facilities. Step 9. Apply for stormwater management permit. Construction Phase Step 10. After receiving approval from county engineer begin construction. Step 11. Coordinate construction with county engineer inspection staff during construction. Post-Construction Phase Step 12. After construction prepare as-built survey and as-built design certification. Step 13. Adjust stormwater structures if necessary. Step 14. Secure certificate of occupancy/final plat. (Ord. No. 2020-1214, ยง 5, 12-14-20) 2. GENERAL LEVEL OF SERVICE STANDARDS 2.1. Detention Requirements.