A permit shall be required to locate a pre-owned or new manufactured home in the county.

(1) Permit. To obtain a permit, applicants shall provide to the building inspector:

a. An application form signed by the applicant containing such information as is required by the county.

b. A signed affidavit that the pre-owned manufactured home meets, or will meet prior to occupancy, all health and safety standards required in section 18-121.

The building official will also require other information reasonably necessary to assure compliance with the minimum health and safety standards, including photographs of the exterior and each room of the interior of the home. The building official can require additional information to determine compliance with section 18-121.

c. The permit and inspection fee required by subsection (4).

(2) Inspection. Upon receipt of a permit, applicants may relocate the manufactured home to a residential site for purposes of inspection. Applicant shall arrange for an inspection to be held after the installation of the manufactured home is complete.

(3) Alternative inspection. At the request of the applicant, the building official may, at his or her discretion, inspect a pre-owned manufactured home prior to its being relocated if the home is then located within the county. An on-site inspection surcharge shall be charged for this inspection in addition to the regular fees set forth in subsection (4) below. The manufactured home shall still be required to be inspected after installation.

(4) Fees. A permit and inspection fee shall be charged to the application to cover the cost to the county to process the permit application and inspect the pre-owned manufactured home once installed. Such fee shall cover the initial inspection and one follow-up inspection. The applicant shall be charged a fee for each additional follow up inspection that may be necessary. A $250.00 penalty will be added to permits where the mobile home was brought on the lot before an installation permit was obtained.

(5) Certificate of completion. A certificate of completion shall be issued to the applicant at such time that the building official certifies that the requirements of this division have been met. In the event the manufactured home, once installed, cannot meet the requirements of this division, it either must be repaired to comply with the standards herein or removed.

(6) Removal of home in violation of this section. A manufactured home that fails to meet the minimum health and safety standards in section 18-121, or fails to obtain an installation permit prior to a home being brought onsite, must be removed by the owner within 14 days of written notice by the building official or code enforcement officer. The county shall seek an order from the magistrate court, or from a court of competent jurisdiction to remove the home from the subject property, and place the costs associated with removal as a lien against the property. The owner of the home and/or property is also subject to citations, with a fine of up to $1,000.00.

History

The history line the source prints at the end of the section.

(Ord. of 6-4-2008, § I; Ord. of 9-1-2010, § I; Ord. of 12-13-2017, § II; Ord. of 11-4-2020(2), §§ I, II)

Read this code where it is posted (Municode) The source is the county's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:bartow-county/code/18-120@2026-09-02-00bd9e1b77

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.