Construction of manufactured homes is regulated by federal law and not this chapter.

However, installation of manufactured homes must meet manufacturer's specifications and the requirements of this paragraph and the zoning ordinance before permanent utilities may be installed. An installation permit must be obtained prior to installation and an inspection must occur of the installation, including utility connections and underpinning, prior to issuance of a certificate of occupancy.

(1) Installation requirements. Manufactured homes must be installed with O.C.G.A.

§ 8-2-160 and the regulations promulgated thereunder. Installation shall be finalized within 120 days of obtaining an installation permit.

(2) Utility connections. Utility connections prior to the final inspection of the installation will be considered temporary and will be approved only when arrangements for complete installations have been made.

(3) Entry landing. All manufactured house installations shall provide an adequate means of entry (including steps and a landing at each doorway).

(4) Sewage management. A septic permit or a sewer tap must be secured and provided to building inspections before an installation permit for a manufactured home will be permitted.

(5) Underpinning. Except as otherwise provided herein, any manufactured house, whether on an individual lot or in a manufactured house subdivision, shall be required to be underpinned prior to occupancy.

a. The underpinning shall consist of one of the following: masonry (for example, brick, stone, rock, concrete block) or such other material as may be approved by the building official prior to installation. The following types of materials are not permitted to be used, including, but not limited to, tin, wood, plastic sheeting or gypsum board (black board), vinyl siding/panels or aluminum siding/panels.

b. The underpinning must be adequately secured to the manufactured house and where necessary for stability, secured to the ground. Two access doors are required to be installed in a manner which will provide adequate access for inspections and maintenance. Provisions must be made for proper ventilation for the crawl space underneath the manufactured house. The axels and towing tongue must be removed.

History

The history line the source prints at the end of the section.

(Ord. of 1-3-2007(1); Ord. of 6-4-2008, § II; Ord. of 12-13-2017, § II)

Read this code where it is posted (Municode) The source is the county's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:bartow-county/code/18-122@2026-09-02-4703d25f50

The assistant can say what this section says in this edition, quoting it and linking to it. It will not apply the law to your situation, and nothing here is legal advice.

Bartow County Code of Ordinances, Sec. 18-122. Installation of manufactured homes | Georgia Commons