(a) Timeframe on application. Land disturbance permits shall be issued or denied as soon as practicable but in any event not later than 45 days after receipt by the county of a complete and valid application, providing variances and bonding are obtained, where necessary and all applicable fee have been paid prior to issuance. The permit shall include conditions, under which the activity may be undertaken. (b) No issuance without compliance. No land disturbance permit shall be issued by the county unless the erosion, sedimentation and pollution control plan has been approved by the district and the county has affirmatively determined that the plan is in compliance with this article, any variances required by subsections 34-267(c)(15) and (16) are obtained, surety requirements per subsection 34-281(f) are met, and all ordinances and rules and regulations in effect within the county are met. If the permit is denied, the reason for denial shall be furnished the applicant. (c) Any land-disturbing activities by a local issuing authority shall be subject to the same requirements of this article, and any other ordinances relating to land development, as are applied to private persons and the division shall enforce such requirements upon the local issuing authority. (d) Multi-phase developments. If the tract is to be developed in phases, then a separate land disturbance permit shall be required for each phase. Individual lots shall not count as separate phases. (e) Suspension, revocation or modification. The land disturbance permit may be suspended, revoked, or modified by the county as to all or any portion of the land affected by the plan, upon finding that the holder or his successor in title is not in compliance with the approved erosion, sedimentation and pollution control plan or that the holder or his successor in title is in violation of this article. A land disturbance permit may be revoked upon a finding by the county engineer that the owner, operator, applicant or permit holder is in violation of the county zoning ordinance, or the county flood damage prevention Ordinance. A holder of a land disturbance permit shall notify any successor in title to him as to all or any portion of the land affected by the approved plan of the conditions contained in the permit. See subsection 34-297(a) of this article. (f) The LIA may reject a permit application if the applicant has had two or more violations of previous permits or the Erosion and Sedimentation Act permit requirements within three years prior to the date of the application, in light of O.C.G.A. § 12-7-7(f)(1). (g) Certification of payment of taxes. No land disturbance permit shall be issued unless the applicant provides a statement by the tax commissioner of the county certifying that all ad valorem taxes levied against the property and due and owing have been paid. (h) Submission of false information. It shall be a violation of this article to make a false certification under sections 34-282 or 34-283 of this article, or to knowingly submit false information on a site plan or application for a land disturbance permit. (i) No activity prior to permit issuance. It shall be unlawful to commence any land disturbance activity for the construction of any building; to commence construction of any building; to commence the moving or alteration of any building; or to commence the development of land for a use not requiring a building, until all necessary permits for such work have been issued. All land development or construction shall comply with the codes and ordinances in effect in the county at the time the permit is issued. (j) Predesign meeting. Engineers and developers are required to schedule a predesign meeting with representatives of the development review committee for a consultation meeting at the time of the preliminary plan of subdivision or other early step in the development process. The purpose of this meeting is to discuss and assess constraints, opportunities and potential ideas for erosion control designs before the formal site design engineering is commenced. CD34:53 Supp. No. 9 (k) Preconstruction conference. Once the construction plans are approved, no permit for land disturbing activity will be issued to an applicant without the applicant first attending an on-site mandatory preconstruction conference with a representative from the county. (l) Erosion and sediment control inspection permit. The county requires all new residential home sites and additions to obtain an erosion and sediment control inspection permit. This permit approval is required prior to undertaking any clearing activity as may be deemed necessary prior to the issuance of an approved residential drainage plan or building permit as outlined in the county development regulations (Appendix B to this Code). The requirements of said E&S inspection permit shall be met prior to recording of final plat, final as-built or release of a certificate of occupancy. Fees for this permit shall be as established by resolution of the county commissioner. (m) Additional land disturbance permit requirements. In addition to the requirements of this article, the county requires all new development or redevelopment projects creating or replacing more than 5,000 square feet of impervious surface to obtain a stormwater management permit as required by the county stormwater management ordinance (section 34-551 et seq.). This permit is required prior to undertaking any clearing or grading activity for projects exceeding the above listed requirements. All stormwater management permits will be required to follow the construction erosion, sedimentation and pollution control plan submitted and approved by the district (district approval required only on projects disturbing more than one acre) and county engineer. (n) Properly displaying permits. Permits for all development must be displayed prior to beginning any clearing or grading for any residential or non-residential development project. All building permits must be displayed prior to beginning any building construction. Such permits must be placed on a post or other structure at least three feet off the ground and no more than two feet back from the right-of-way, so as to be easily visible to the inspectors and passers-by. Such permits must be encased in a waterproof container to protect them from the elements, and must be legible. The permittee shall be responsible for ensuring a clear and legible permit is on display at all times. In the event of damage or loss, a replacement permit shall be immediately obtained and displayed. Failure to comply with this provision shall result in an administrative fine of $250.00, and the permit and all subsequent inspections shall be suspended until such fine is paid. (o) Monthly E&S report. Upon the issuance of the land disturbance permit, the operator shall ensure that a monthly erosion and sedimentation report outlining the status of the project is delivered to the county on or before the first business day of each month. The report will be prepared by a qualified professional engineer/architect/landscape architect/ certified professional in erosion and sediment control (CPESC) or an individual meeting the education and certification requirements of section 34-312 of this article. At minimum, individuals involved in development inspections should be certified as Level 1B. All initial inspections and proposed modifications to structural practices (BMPs) shall be certified by a Level 2 design professional. Should this report not be received by 5:00 p.m. on the said dates, a stop work order along with an administrative fine of $250.00 may be issued for the project. The permit and all subsequent inspections shall be suspended until such fine is paid. Should the monthly project report fail to meet the requirements of this article, a five-day write up will be issued for the project and a follow up inspection may be required within five days of said report to ensure site is brought into compliance with the requirements of this article. Monthly reports are required to be submitted for the project or each phase of the project until proof of the notice of termination, as defined as �accepted� by the NPDES general permit, as filed with the Georgia EPD is submitted to the county. (p) Residential drainage plan. A residential drainage plan (RDP) accepted by the county shall be required prior to issuance of a building permit on those lots subject to periodic or nuisance flooding or as labeled �RDP� on a final plat. The residential drainage plan shall meet the requirements as outlined in the county development regulations (Appendix B to this Code).