Sec. 34-298. Variances.

About this text

  • As published by Municode, current through 2026-09-02
  • The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.

(a) Process. Requests for variances from the requirements of this article shall be heard initially by the county engineer. Variances defined as available only from the EPD director cannot be granted by the county engineer. Any variance given by the director may also be required an additional variance approval by the county engineer, considering the criteria in this section, prior to implementation. See the county stream buffer protection ordinance.

(b) Criteria. In reviewing application for variances, the county engineer shall consider all technical evaluations, all relevant factors, and all standards specified in this and other sections of this article. A variance shall only be granted upon (i) a determination that the variance is the result of topography or other hardship beyond the applicant's control, (ii) a determination that failure to grant the variance would result in exceptional hardship, (iii) a determination that the granting of a variance will not result in increased erosion, stormwater run-off, additional threats to public safety, extraordinary public expense, create a nuisance, cause fraud on or victimization of the public, or conflict with existing laws or ordinances; (iv) a determination that the variance will not have a negative impact based on the criteria in subsection (c) below; and (v) a determination the variance is the minimum necessary to afford relief. A variance to allow permanent vegetation to be installed after issuance of a certificate of occupancy shall have a duration of no longer than six months.

(c) Specific negative impact factors. The specific negative impact factors to be considered are as follows:

(1) The possibility that, given the variance, erosion, sedimentation or stormwater run-off will affect or injure the lands of others;

(2) The danger to life and property due to erosion damage;

(3) The availability of alternative options, reconfigurations, and other measures that would achieve erosion and sedimentation control without a variance;

(4) The potential for increased maintenance costs subsequent to completion of the development;

(5) The negative impacts that the proposed variance would create;

(6) The purposes of the requirement and this article.

(d) Conditions. Upon consideration of the factors listed above, and the purposes of this article, the county engineer may attach such conditions to the granting of a variance as he deems necessary to further the purposes of this article.

(e) Appeals. Appeals of denial or grant of a variance may proceed according to section 34-299 of this article.

History

The history line the source prints at the end of the section.

(Ord. of 12-7-2016)

Read this code where it is posted (Municode) The source is the county's code as its publisher or its own website posts it. Check it there for later changes.

Version local-code:bartow-county/code/34-298@2026-09-02-413edbe127