Bartow County · Code of Ordinances
Chapter 55 - ROADS AND BRIDGES / Article IV - BROADBAND READY COMMUNITY
Sec. 55-73. Application completeness review.
About this text
- As published by Municode, current through 2026-09-02
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
(a) Bartow County shall determine whether an application is incomplete and notify the applicant, by email, of the determination by Bartow County within ten calendar days of receiving an application for a broadband network project. The application shall be pursuant to the relevant Code provisions, but notice must also be simultaneously given to the single point of contact by email, referencing this article.
(b) If Bartow County does not respond to the applicant on whether the application is incomplete, within ten calendar days, the application shall be assumed to be complete on the 11th day.
CD55:13 Supp. No. 14
(c) The applicant shall inform the county of any application it submits that it is intended to be an application subject to this article, so that the county may be aware of the expedited timelines. The provisions of this article shall only apply if invoked by the applicant.
History
(Ord. of 2-10-2021(3), § I)
Read this code where it is posted (Municode) The source is the county's code as its publisher or its own website posts it. Check it there for later changes.