Sec. 22-124. Permits.
About this text
- As published by Municode, current through 2010-11-09
- The enacted text only: the publisher's notes (editor's notes, state law references, cross references) are not included.
(a) Application for building permit. Any applications for building permits shall be accompanied by two site plans drawn to scale showing the actual dimensions of the lot to be built upon, the size and location of the proposed buildings, and any proposed land disturbing activities as may be essential for determining whether the provisions of this article are being observed. This information is required on the site plan before the site plan is considered by the county manager and/or his designee and any local permits are approved.
(b) Expiration of building permit. Any building permit shall become void if the work involved has not begun within six months after the date of issuance of the permit or if the work or development authorized by such permit is suspended or abandoned for a period of six months after the work or development is commenced, provided that extensions of time for periods not exceeding six months each may be allowed in writing by the county manager and/or his designee.
(c) Expiration of development permit. If construction described in the development permit has not commenced within six months from the date of issuance, the permit shall expire. If construction described in the development permit is suspended or abandoned after work has commenced, the permit shall expire six months after the date that work ceased.
(d) Appeals. Appeals on decisions on permit applications made by the county manager and/or his designee may be made to the board of commissioners, but only after review and recommendation of the Greater Berrien Planning Commission. The appeal must be made within ten days of the decision rendered by the county manager and/or his designee. A public hearing shall be held for such administrative appeals. Public announcement of the hearing shall be printed in the county official legal organ at least 15 but not more than 45 days prior to the hearing. Any person may offer testimony at the hearing. The decision of the board of commissioners may be appealed to a court of competent jurisdiction, as provided in state law.
(e) Judicial review. All decisions of the board of commissioners concerning denial, approval, or conditional approval of a permit shall be renewable in the proper courts as provided by law.
History
(Ord. of 11-27-2000, §§ 1-7, 1-10, 1-11, 1-14)
Read this code where it is posted (Municode) The source is the county's code as its publisher or its own website posts it. Check it there for later changes.